Explanation
This legislation authorizes the Public Service Director to enter into a contract for the Transportation Division with Decker Construction Company in the amount of $2,631,479.98 for the Resurfacing 2003 Project #3 - OPWC project and to pay construction inspection costs up to $254,567.50. This improvement details the resurfacing of various streets and related curb ramps located citywide. The Notice to Proceed will likely be issued by October 15, 2003. The project is to be completed within 270 calendar days. This project was bid by the Transportation Division and was advertised in The City Bulletin, Dodge Reports, and by the Builders Exchange. Six (6) responsive bids were received (5 majority, 1 minority) and tabulated on August 8, 2003, as follows (prices reflect the base bid plus Alternate #1):
Decker Construction Company $2,631,479.98
Columbus Asphalt Paving Company $2,688,978.61
Miller Pavement Maintenance, Incorporated $2,705,813.05
Strawser Paving $2,863,164.47
McDaniels Construction Corporation, Incorporated $2,905,813.82*
Shelly and Sands, Incorporated $2,938,520.73
* MBE
Award is to be made to Decker Construction Company, C.C. No. 31-0983557 (expires July 7, 2006), as the lowest, best, most responsive, and most responsible bidder using responsible contractor criteria. Construction inspection is budgeted at $254,567.50.
The Ohio Public Works Commission has approved funding a portion of the ADA-compliant handicapped ramp work connected with this and other resurfacing projects planned for award in 2003 up to a maximum of $4,389,627.00. The eligible ramp work on this contract has been estimated at $987,859.95. Local matching funds for this project are budgeted in the street resurfacing proj...