Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to execute a planned contract modification (#3) for professional engineering services with DLZ Ohio, Inc. in connection with the Olentangy-Scioto Interceptor Sewer (OSIS) Augmentation and Relief Sewer (OARS); to authorize the appropriation and transfer of $2,139,082.82 from the Sanitary Sewer Reserve Fund to the Voted Sanitary Sewer Bond Fund; to authorize the expenditure of $2,139,082.82 from the Voted Sanitary Sewer Bond Fund; and to amend the 2009 Capital Improvements Budget.
The purpose of this Modification (#3) is to complete final design engineering services associated with implementing significant revisions to the design concept. Modification #1 authorized the completion of a new Design Report to fully evaluate the deep tunnel alternative. Modification #2 authorized the final design of the OARS deep tunnel facilities. Contingency funds were utilized to revise the alignment to the Moler Street Regulator side of the river, to complete the Value Engineering Workshop, and to complete the Surge Analysis. This Modification (#3) will allow for revision to the design scope to incorporate the recommendations of the Value Engineering Workshop, design modifications from the Surge Analysis, modifications based upon subsequent reviews, and implementing a two-phased construction contract approach for the project.
The original contract for DLZ Ohio, Inc. was for the design of Phase 1 of the OSIS Augmentation and Relief Sewer (OARS). The work included the design of a 15,000 foot long large diameter conduit via open-cut methods and other facilities and appurtenances to convey Combined Sewer flows from the vicinity of the Whittier Street Storm Standby Tanks south to the vicinity of the Jackson Pike Wastewater Treatment Plant.
Due to the large cost and long duration associated with the design of this project, the contract was established to be funded incrementally. The prop...
Click here for full text