Explanation
The purpose of this legislation is to authorize the Director of Finance and Management to establish a Blanket Purchase Order for Sludge Grinder Equipment Repair Parts and Services in accordance with an established Universal Term Contract for the Division of Sewerage and Drainage, Jackson Pike Wastewater Treatment Plant and Sewer Maintenance Operation Center.
Sludge Grinder parts are required for the sludge grinders located at the Jackson Pike Wastewater Treatment Plant. Primary Sludge is processed by these grinders which are placed in areas to reduce the down time of pumps, pipe lines, and valves, and to protect them from damage or stoppage from large material in the sludge. In 2009 the Jackson Pike Wastewater Treatment Plant maintenance personnel began major rehabilitation projects on the grinders at that plant. The plant has a need for additional money to complete the rehabilitation projects. In addition, the Sewer Maintenance Operation Center has a need for services on a grinder at Dodge Park and additional monies are needed for the project.
The Division of Sewerage and Drainage desires to establish a Blanket Purchase Order in accordance with the existing Universal Term Contract. The contract number is FL-004295 which expires on May 31, 2011.
SUPPLIER: JWC Environmental, Contract Compliance No. (33-0381716) Expires 9-28-11
FISCAL IMPACT: $67,000.00 is needed and budgeted for this purchase. The Division of Sewerage and Drainage has certified the maximum amount allowed to be certified against a Universal Term Contract within the Columbus City Code without legislation.
$96,200.00 has been certified against this UTC in 2009
$63,626.00 was spent in 2008
$91,418.00 was spent in 2007
The company is not debarred according to the Excluded Party Listing System of the Federal Government or prohibited from being awarded a contract according to the Auditor of State Unresolved Findings for Recovery Certified Search.