Explanation
BACKGROUND: This ordinance authorizes the Public Utilities Director to modify and increase a professional services contract with EMH&T, Inc. for Geographic Information System (GIS) data conversion services for the Division of Power and Water. The intent of this project is to perform a data conversion service necessary to populate the GIS database with water infrastructure assets covering the entire utility service area. This ordinance requests authority to modify the contract to include mapping of underground electrical circuits in the downtown area of the City. While the original contract scope included mapping only water infrastructure the electrical systems are in close proximity and can easily be mapped and entered into the database. Accurate maps of existing underground circuits are critical to being able to rapidly respond for maintenance and repairs of these circuits and to accurately be able to provide circuit locations to contractors, developers, and property owners. This modification is a logical extension of the GIS scope of work contained in the contract. This project supports the directives of the Department of Public Utilities's (DPU) Technology Master Plan which includes completion of the conversion of water utility data and the Computerized Maintenance Management System (CMMS).
1. Amount of additional funds to be expended: $86,900.00
Original Contract Amount: $3,775,000.00
Amount of original contract and this modification: $3,861,900.00
2. Reasons additional goods/services could not be foreseen:
The original RFP from 2005 included the task of data conversion service necessary to populate the GIS database with water infrastructure assets covering the entire utility service area. The task of mapping electrical circuits requires the same identification and data enty into the same database.
3. Reason other procurement processes are not used:
Since the original RFP included the task of data conversion ser...
Click here for full text