header-left
File #: 0057-2008    Version: 1
Type: Ordinance Status: Passed
File created: 1/3/2008 In control: Utilities Committee
On agenda: 2/4/2008 Final action: 2/6/2008
Title: To authorize the Director of Public Utilities to execute a construction contract with U.S. Utility Contractor Company in the amount of $292,000.00 for the Harrisburg Pike 69 KV and 15 KV Relocation Project; to provide for Prevailing Wage coordination services to the Transportation Division in the amount of $500.00; for the Division of Power and Water (Power); to authorize the transfer of funds and an expenditure of $292,500.00 within the Voted Street Lighting and Electricity Distribution Improvements Fund, and to declare an emergency. ($292,500.00)
Attachments: 1. ORD 0057-2008 Bid Tab.pdf, 2. ORD 0057-2008 QFF.pdf, 3. ORD 0057-2008 Legislation Information Sheet.pdf, 4. ORD 0057-2008 map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
2/6/20081 MAYOR Signed  Action details Meeting details
2/6/20081 CITY CLERK Attest  Action details Meeting details
2/4/20081 Columbus City Council ApprovedPass Action details Meeting details
2/4/20081 COUNCIL PRESIDENT Signed  Action details Meeting details
1/24/20081 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
1/24/20081 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
1/24/20081 Utilities Drafter Sent for Approval  Action details Meeting details
1/24/20081 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
1/24/20081 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
1/22/20081 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
1/22/20081 Utilities Drafter Sent for Approval  Action details Meeting details
1/22/20081 Auditor Reviewer Reviewed and Approved  Action details Meeting details
1/22/20081 CITY AUDITOR Reviewed and Approved  Action details Meeting details
1/22/20081 Utilities Drafter Sent for Approval  Action details Meeting details
1/18/20081 Finance Reviewer Reviewed and Approved  Action details Meeting details
1/16/20081 Utilities Drafter Sent for Approval  Action details Meeting details
1/15/20081 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
1/9/20081 Utilities Reviewer Sent for Approval  Action details Meeting details
1/8/20081 Utilities Drafter Sent for Approval  Action details Meeting details
1/8/20081 Utilities Reviewer Reviewed and Approved  Action details Meeting details
1/8/20081 Utilities Drafter Sent for Approval  Action details Meeting details
1/7/20081 Utilities Reviewer Reviewed and Approved  Action details Meeting details
1/7/20081 Utilities Reviewer Reviewed and Approved  Action details Meeting details
1/3/20081 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with U.S. Utility Contractor Company in the amount of $292,000; to encumber funds with the Transportation Division for prevailing wage coordination services in the amount of $500.00, for a legislative total of $292,500.00; in connection with the Harrisburg Pike 69 KV and 15 KV Circuit Relocation Project in support of an Ohio Department of Transportation (ODOT) Road Improvement Project.

2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened three bids on December 19, 2007. Bids were received from U.S. Utility Contractor Company - $292,000.00; Vaughn Industries - $399,250.00; and Quality Lines, Inc. - $525,000.00

The lowest and best bid was from U.S. Utility Contractor Company in the amount of $292,000.00. Their Contract Compliance Number is 34-1606689 (expires 3/2/08, F1). Additional information regarding all bidders, description of work, contract time frame and detailed amounts can be found on the attached Legislation Information Form.

3. Emergency Designation: It is requested that this Ordinance be handled in an emergency manner as construction needs to be completed by ODOT's May deadline, or charges may be incurred.

4. FISCAL IMPACT: This legislation includes a transfer of funds within the Voted Street Lighting and Electricity Distribution Improvements Fund and an amendment to the 2007 Capital Improvements Budget.


Title

To authorize the Director of Public Utilities to execute a construction contract with U.S. Utility Contractor Company in the amount of $292,000.00 for the Harrisburg Pike 69 KV and 15 KV Relocation Project; to provide for Prevailing Wage coordination services to the Transportation Division in the amount of $500.00; for the Division of Power and Water (Power); to authorize the transfer of funds and an expenditure of $292,500.00 within the Voted Street Lighting a...