Explanation
Seventeen (17) arches were installed over North High Street as the essence of the Short North Arch project. This project was funded by a combination of city money and funding from private sources. The private funds were deposited into the Short North Special Improvement District Fund. Construction was authorized by Ordinance 0144-2001 passed by City Council January 29, 2001.
Subsequent to installation of the arches, the fiber optic lighting system failed to function properly. The City has determined that it is necessary to engage additional engineering services in connection with the project.
Although the City informally evaluated several firms, the firm was chosen outside the standard consultant selection process due to the time-sensitive nature of the project as well as the limited availability of the engineering firms that specialize in lighting systems, including fiber optic lighting. This selection will require a waiver of the formal competitive bidding process prescribed by Section 329 of the Columbus City Code.
Ralph and Curl Engineer's contract compliance number is 31-1067613 and expires February 14, 2004.
Based upon discussions with Ralph and Curl Engineers, it is estimated that $87,260.00 is needed for this contract. Funding is available within the Short North Special Improvement District Fund, Fund 716, utilizing private monies. The City is involved in litigation with the original design firm and other entities, and recovery of this amount will be sought.
Emergency action is requested to allow Ralph and Curl Engineers to proceed with the work as quickly as possible in order to restore the lighting system to operational status in the shortest possible timeframe.
Title
To appropriate $87,260.00 from the Short North Special Improvement District Fund; to authorize the Public Service Director to enter into a contract with Ralph and Curl Engineers to provide engineering services in connection with the Short North ...
Click here for full text