Explanation
The purpose of this legislation is to authorize the Director of Public Utilities to enter into contract for concrete and structural repairs at the Whittier Street River By-Pass and South Abutment area with McDaniel's Construction Corp. Inc, for the Division of Sewerage and Drainage, Jackson Pike Wastewater Treatment Plant. The amount being requested includes contingency monies for the project.
The Whittier Street River By-Pass and South Abutment area located at 155 W. Whittier Street has deteriorating infrastructure that is in need of concrete and structural repairs. The Director of Public Utilities opened formal bids on October 6, 2004. Four (4) bids were received. The apparent low bidder, Quality Masonry was deemed non-responsive for not submitting a Contract Compliance Application with their bid proposal as specified in the Tier I Section of the Qualification and Resource Factors. Furthermore, the Engineering Evaluation Team deemed that Quality Masonry does not have the resources or the experience to adequately perform this project. A tabulation of those bids is as follows:
Quality Masonry: $161,050.00 (NR)
McDaniel's Construction Corp Inc. $182,209.00
General Maintenance: $183,593.00
The Righter Co. $278,200.00
SUPPLIER: McDaniel's Construction Corp. Inc (31-1145406)
FISCAL IMPACT: $218,209.00 is needed and budgeted for this project. Total amount needed includes contingency money.
Emergency legislation is being requested so that work can begin at the earliest time available.
Title
To authorize the Director of Public Utilities to enter into contract with McDaniel's Construction Corp Inc. for the Whittier Street River By-Pass and South Abutment Project for the Division of Sewerage and Drainage, to authorize the expenditure of $218,209.00 from the Sewerage System Operating Fund, and to declare an emergency. ($218,209.00)
Body
WHEREAS, the Whittier Street River By-Pass and South Abutment area located at 155 W. ...