File #: 0719-2009    Version: 1
Type: Ordinance Status: Passed
File created: 5/7/2009 In control: Utilities Committee
On agenda: 6/1/2009 Final action: 6/3/2009
Title: To authorize the Director of Public Utilities to modify and increase the construction contract with Complete General Construction Company due to unforeseen conditions found during construction of the Fulton Street/Franklin County Courthouse 15 KV Circuit Relocation for the Division of Power and Water; to amend the 2008 Capital Improvement Budget: to authorize a transfer and expenditure of $78,815.00 within the Division of Power and Water's Electricity Permanent Improvement Fund (Non-Bond); and to declare an emergency. ($78,815.00)
Attachments: 1. Request for CIP Legislation Form (Revised 7-26-07)7.pdf, 2. modificationrequest.pdf, 3. FW Fulton St Revised Contract Proposalapproval.htm, 4. Franklin Co. Courthouse Revised Schedule.pdf, 5. Copy of Fulton St 15kv Revised Schedule.pdf, 6. FW Fulton St Revised Contract Proposal.txt
Date Ver.Action ByActionResultAction DetailsMeeting Details
6/3/20091 MAYOR Signed  Action details Meeting details
6/3/20091 CITY CLERK Attest  Action details Meeting details
6/1/20091 Columbus City Council ApprovedPass Action details Meeting details
6/1/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
5/18/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/18/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
5/18/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
5/18/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/18/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
5/18/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
5/15/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
5/15/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
5/14/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/13/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
5/13/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/13/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
5/12/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
5/11/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/8/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
5/8/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/8/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
5/7/20091 Utilities Drafter Sent for Approval  Action details Meeting details
5/7/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation

BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase the construction contract with Complete General Construction Company for the Fulton St./Franklin County Courthouse 15 KV Circuit Relocation Project, for the Division of Power and Water. At this time, the complete estimated cost breakdown is as follows:

· $110,150.00 - Open cut installation of 6-5" PVC concrete encased conduit
· ($38,500.00) - Credit given by Complete General for not being able to install the conduit through boring. (as was included in the original construction contract)
· $7,165.00 - 10% Contingency

The total amount of this modification is $78,815.00, a 73.5% increase from the original contract.

1. Amount of additional funds to be expended: $78,815.00
Original Contract Amount: $107,250.00
Amount of original contract and this modification: $186,065.00

2. Reasons additional goods/services could not be foreseen:
· The original contract price was based upon installation of the conduit through the means of underground boring. The bore was begun and proceeded approximately forty feet before the boring machine encountered signal interference.
· Interference with the boring machine's signal causes a significant safety issue in that the boring machine operator is unable to detect underground obstructions and may hit other buried utility lines.
· Multiple agencies including the contractor, Franklin County engineers, City of Columbus experts and the boring machine manufacturer attempted to locate, isolate and turn off the interference with no success.
· No one anticipated the signal interference. The boring machine manufacturer concluded that the interference was caused by significant cellular broadband usage in the area of the Franklin County Courthouse.

To complete the installation the construction had to be changed to open cut to install duct banks and the required conduit.

3. Reason other procurement proce...