Title: To authorize the Director of the Department of Public Utilities to enter into construction contract modifications with Travco Construction Inc. and John Eramo & Sons Inc. for the 2024 Water Main Repairs project; to authorize an amendment to the 2024 Capital Improvement Budget; to authorize a transfer of cash and appropriation between projects within the Water Bond Fund; to authorize the expenditure of up to $1,400,000.00 for the project; and to declare an emergency. ($1,400,000.00)
Indexes: MBE Participation
Attachments: 1. ORD 0277-2025 Eramo Utilization, 2. ORD 0277-2025 Travco Utilization, 3. ORD 0277-2025 Accounting Template.pdf
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into construction contract modifications for the 2024 Water Main Repairs project, CIP #690521-100012, with the following companies:
· Travco Construction Inc., in an amount up to $700,000.00.
· Eramo & Sons Inc., in an amount up to $700,000.00.

The scope of work for the contract is not changing. These contracts provide assistance to our water line maintenance crews in completing water main break repairs in a timely matter should the number of breaks exceed our normal maintenance capacities. These additional funds are being added to the original contract amounts due to higher than anticipated breaks occurring, resulting in a higher than anticipated need for outside assistance in making repairs.

The Community Planning Area is 99 - Citywide.

1.1 Amount of additional funds to be expended: $1,400,000.00
The bid amount and award amount for the Travco Construction contract was $768,352.75, including a 10% construction contingency amount. The modification amount for the Travco Construction contract is $700,000.00, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No additional contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

Cost summary: Travco Construction

Original Contract (ORD 3346-2023; PO429625) $768,352.75
Modification No. 1 (This Ordinance) $700,000.00
CONTRACT TOTAL $1,468,352.75

The bid amount and award amount for the John Eramo & Sons Inc. contract was $802,175.00, including a 10% construction contingency amount. The modification amount for John Eramo & Sons Inc. contract is $700,000.00, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No additi...