Title: To authorize the Director of Public Utilities to enter into a construction contract in accordance with the sole source provisions of the Columbus City Code with Siemens Water Technologies Corporation, in connection with the Jackson Pike Wastewater Treatment Plant Digester Cover Rehabilitation project; to authorize the appropriation, transfer and expenditure of $1,512,000.00 from the Sewer System Reserve Fund to the Ohio Water Pollution Control Loan Fund for the Division of Sewerage and Drainage. ($1,512,000.00) (AMENDED BY 0514-2010 PASSED 5/17/2010)
Attachments: 1. DBE Utilization Form J215 DBE 6100-4.pdf, 2. 650250.3Infotobeincludedinto LEGISLATIONC 1-12-09.pdf, 3. Siemems Sole Source Form.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
11/25/20091 MAYOR Signed  Action details Meeting details
11/25/20091 CITY CLERK Attest  Action details Meeting details
11/23/20091 Columbus City Council ApprovedPass Action details Meeting details
11/23/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
11/16/20091 Columbus City Council Read for the First Time  Action details Meeting details
11/2/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
10/30/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
10/30/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
10/30/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/30/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
10/29/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
10/29/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
10/29/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/23/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
10/23/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/22/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/22/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/22/20091 Finance - Purchasing Reviewer Reviewed and Approved  Action details Meeting details
10/21/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
10/21/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/20/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/20/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
10/15/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/15/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/14/20091 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

1. BACKGROUND:

A. Need. This legislation authorizes the Director of Public Utilities to enter into a construction contract with Siemens Water Technologies Corporation, for the Jackson Pike Wastewater Treatment Plant Digester Cover Rehabilitation project for the Division of Sewerage and Drainage. These digester covers are part of the biogas (methane) handling system at the wastewater treatment plant. This is the second phase of a three-year program to rehabilitate the five of the covers and six control systems. The existing Dystor digester covers are near the end of their useful lives and are beginning to experience leakage of flammable biogas. The leaks now render the systems inoperable as designed. These improvements are necessary to provide reliability and continued operational performance for this vital treatment process.

The proposed construction contract with Siemens Water Technologies Corporation is for Contract J215. This contract work consists of replacing the Dystor air and gas membrane covers and the Dystor digester cover control system, rehabilitating the concrete structures and piping systems for Digesters Nos. 5 and 6, along with providing training for the plant personnel to operate the new control system. The identical work will begin on Digesters Nos. 3 and 4 in 2010. This continued work shall be funded by a new contract, negotiated and funded by appropriation in the identified year.

This ordinance is being submitted in accordance with the provisions of Sole Source procurement of the Columbus City Code Section 329.07.

B. Supplier: Siemens Water Technologies Corporation, 04-3063901 | (MAJ) | Expires 12/23/2010

C. Emergency Designation: Emergency designation is not requested.

2. FISCAL IMPACT:

This ordinance authorizes the appropriation, transfer and expenditure of $1,512,000.00 from the Sewer System Reserve Fund 654 to the Water Pollution Control Loan Fund 666 to fund this project expenditure. This transaction is a temporary ...