Explanation
Background:
- Bids were received by the Recreation and Parks Department on September 27, 2005, for the Alum Creek Trail: SR 161 Underpass Project, as follows:
Status Amount
Columbus Asphalt Majority $229,961.85
Shelly and Sands Majority $246,641.90
Strawser Paving Majority $253,666.20
- Project includes new asphalt trail along Alum Creek from Casto Park to Strawberry Farm Park, which includes clearing, new asphalt, concrete curbing, grading, fencing, seeding, landscaping, etc.
- The Contract Compliance Number for Columbus Asphalt is #31-0857095.
- A contingency amount of $20,000.00 is being included in this project.
- Emergency legislation is necessary so initial stages of work can begin in fall 2005 for spring 2006 asphalt work.
Fiscal Impact:
- $249,961.85 is required and budgeted in the Voted 1999/2004 Parks and Recreation Bond Fund to meet the financial obligation of this contract.
Title
To authorize and direct the Director of Recreation and Parks to enter into contract with Columbus Asphalt for the Alum Creek Trail: SR 161 Underpass Project, to authorize the expenditure of $249,961.85 from the Voted 1999/2004 Parks and Recreation Bond Fund, and to declare an emergency. ($249,961.85)
Body
WHEREAS, bids were received by the Recreation and Parks Department on September 27, 2005, and the contract for the Alum Creek Trail: SR 161 Underpass Project will be awarded on the basis of the lowest and best responsive and responsible bidder; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessary enter into contract so initial stages of work need to begin in fall 2005 for spring 2006 asphalt work; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
Section 1. That the Director of Recreation and Parks be and he is hereby authorized and directed to enter into contract with Columbus Asphalt, for the Al...