File #: 0311-2011    Version: 1
Type: Ordinance Status: Passed
File created: 2/16/2011 In control: Public Utilities Committee
On agenda: 4/11/2011 Final action: 4/13/2011
Title: To authorize the Director of Public Utilities to execute a construction contract with UCL, Inc. for the Recoating of the Henderson Road East and West Tank Interiors Project; for the Division of Power and Water; and to authorize a transfer and expenditure of $434,240.00 within the Water Build America Bonds Fund. ($434,240.00)
Attachments: 1. ORD0311-2011 QFF.pdf, 2. ORD0311-2011 Information.pdf, 3. ORD0311-2011 map.pdf, 4. ORD0311-2011 bid tab.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
4/13/20111 CITY CLERK Attest  Action details Meeting details
4/12/20111 MAYOR Signed  Action details Meeting details
4/11/20111 Columbus City Council ApprovedPass Action details Meeting details
4/11/20111 COUNCIL PRESIDENT Signed  Action details Meeting details
4/4/20111 Columbus City Council Read for the First Time  Action details Meeting details
3/18/20111 City Clerk's Office Sent back for Clarification/Correction  Action details Meeting details
3/18/20111 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
3/8/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/8/20111 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
3/8/20111 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
3/4/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/4/20111 EBOCO Reviewer Sent for Approval  Action details Meeting details
3/4/20111 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
3/3/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/3/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/3/20111 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
3/3/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/3/20111 Auditor Reviewer Reviewed and Approved  Action details Meeting details
3/3/20111 CITY AUDITOR Reviewed and Approved  Action details Meeting details
3/2/20111 Utilities Reviewer Sent for Approval  Action details Meeting details
3/2/20111 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
3/2/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/2/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
2/28/20111 Utilities Reviewer Reviewed and Approved  Action details Meeting details
2/28/20111 Utilities Drafter Sent for Approval  Action details Meeting details
2/28/20111 Utilities Drafter Sent for Approval  Action details Meeting details
2/17/20111 Utilities Drafter Sent for Approval  Action details Meeting details
2/16/20111 Utilities Drafter Sent for Approval  Action details Meeting details
2/16/20111 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with UCL, Inc., in the amount of $434,240.00, for the Recoating of the Henderson Road East and West Tank Interiors Project, Division of Power and Water Contract Number 1173.

This project consists of spot prepare, prime and full overcoat of the interior dry areas as well as removing and replacing the interior wet area coating systems of both the east and west 1 million gallon elevated tanks, as well as minor tank.

2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened seven bids on February 9, 2011. Bids were received from: UCL, Inc. - $434,240.00; George Kountoupes Painting co. - $590,585.00; TMI Coatings, Inc. - $1,173,000.00; Classic Protective Coatings, Inc. - $2,377,395.00; American Suncraft Construction Co. - $4,861,077.60; L.C. United Painting Co. - $235,175.00 (non-responsive); and V & T Painting, LLC - $1,761,110.00 (non-responsive).

The lowest, best, most responsive, responsible bid was from UCL, Inc. in the amount of $434,240.00. Their Contract Compliance Number is 31-1697362 (2/15/13, Majority). Additional information regarding each bidder, description of work, contract time frame and detailed amounts can be found on the attached Legislation Information Form.

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against UCL, Inc.

3. FISCAL IMPACT: A transfer of funds within the Water Build America Bonds Fund will be necessary.


Title

To authorize the Director of Public Utilities to execute a construction contract with UCL, Inc. for the Recoating of the Henderson Road East and West Tank Interiors Project; for the Division of Power and Water; and to authorize a transfer and expenditure of $434,240.00 within the Water Build America Bonds Fund. ($434,240.00)


Body

WHEREAS, seven bids for the Recoating ...

Click here for full text