Explanation
BACKGROUND: This legislation authorizes the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with Ultimax, Inc., for the renovation of the Refuse Collection Division Administrative Building, 2100 Alum Creek Drive. The renovation includes, but is not limited to, carpentry, millwork, furniture, flooring, selective demolition and electrical work.
Formal bids were solicited and thirteen (13) companies submitted bids on January 29, 2009 as follows (0 MBE, 1 ^FBE):
Ultimax, Inc. $74,520.00
Good Home Maintenance, Inc. $77,773.00
Affinia Development, LLC $78,160.00
Swartsell Construction LLC $82,395.00
Steeltree Construction, Inc. $83,200.00
Anderson & Noland Company, Inc. $88,495.00
^Bomar Construction Company, Inc. $88,993.00
Robertson Construction Service, Inc. $89,000.00
Elford, Inc. $90,101.00
Greater Columbus Construction, Inc. $90,300.00
Pro Con Construction Service $91,733.00
Tyevco, Inc. $94,380.00
Ardmore Construction $96,871.00
The Office of Construction Management recommends the bid award be made to the most responsive and responsible and best bidder, Ultimax, Inc.
Ultimax, Inc. Contract Compliance Number 31-1684389 Expiration date July 13, 2009.
This legislation requests permission and authorization for the City Auditor to reallocate funds from an existing Auditor's Certificate (Ac025391), in the amount of $31,000.00.
This legislation also authorizes the Finance and Management Director to expend $3,100.00 or so much thereof as may be necessary to reimburse the General Fund for construction and building renovation expenses incurred by the Office of Construction Management. The Office tracks the hours that each employee works on individual projects and bills these hours back to the proper capital project.
FISCAL IMPACT: The Public Service Depa...