Explanation
 BACKGROUND: This project consists of demolishing a pump station and constructing ~ 6,000 feet of 15’’ to 24’’ sanitary sewer via open cut and Jack-and-Bore near the Rickenbacker Airport, and other  such work as may  be  necessary  to  complete  the  contract, in accordance with the drawings, technical specifications, special provisions, and City of Columbus Construction and Material specifications set forth in this Invitation For Bid (IFB).
Planning Area - 64 - Far South 
PROJECT TIMELINE: All work shall be substantially complete within 270 calendar days of the Notice to Proceed, with final completion to occur within 365 calendar days. The City anticipates issuing a Notice  to  Proceed on or about January 6th. 
PROCUREMENT INFORMATION: The Division advertised for competitive bids submission for the subject services on the City's Vendor Services website and in the City Bulletin in accordance with the overall provisions of Chapter 329 of the Columbus City Code. The Division of Sewerage and Drainage received four (4) bids on September 29, 2022 from the following:  
NAME	TAX ID	DAX #	City/State	Status	Expiration	
Kokosing Construction 	31-1023518	004610	Columbus, OH	MAJ	3/3/2024	
Complete General Construction	31-4366382	006056	Columbus, OH	MAJ	6/8/2023	
Trucco Construction Co., Inc.	31-1293605	004988	Delaware, OH	MAJ	1/23/2024	
John Eramo & Sons, Inc	31-0724866	004251	Hilliard, OH	MAJ	12/9/2023	  
EMERGENCY DESIGNATION is not requested at this time.  
ECONOMIC / ENVIRONMENTAL IMPACT: This project will provide City sanitary sewer service to a quickly developing service area and remove a pump station from our system.  This project will increase the water quality by eliminating potential ground water pollution by preventing the installation of package treatment systems.  This project will also lower the City's operation and maintenance costs by eliminating future O&M and replacement of the existing Military Pump Station (SA-18).  In addition, the proj...