Explanation
Background:
A modification to an agreement with the Ohio Department of Transportation is needed for additional construction related to the Alum Creek Bikeway: I270 to St. Rt. 161, Project Number 21091.
Amount of modification is $210,571.98 bringing the total modified contract cost to $707,277.98.
Emergency legislation is requested to enable project to be closed out and ODOT paid for additional project costs.
Fiscal Impact:
$210,517.98 is required and budgeted in the Parks and Recreation Voted 1999/2004 Bond Fund to meet the financial obligation of this agreement modification.
Title
To authorize and direct the Director of Recreation and Parks to modify the agreement with the Ohio Department of Transportation for additional construction services related to the Alum Creek Bikeway: I270 to St. Rt. 162, Project Number 21091, to authorize the expenditure of $210,517.98 from the Parks and Recreation Voted 1999/2004 Bond Fund, and to declare an emergency. ($210,517.98)
Body
WHEREAS, it is necessary to modify the agreement with the Ohio Department of Transportation for additional construction services related to the Alum Creek Bikeway: I270 to St. Rt. 161, Project Number 21091; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessary to modify said agreement to enable project to be closed out and ODOT paid for additional project costs; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
Section 1. That the Director of Recreation and Parks be and he is hereby authorized and directed to modify an the agreement with the Ohio Department of Transsportation for additional construction services related to the Alum Creek Bikeway: I270 to St. Rt. 161, in accordance with plans and specifications on file in the Recreation and Parks Department.
Section 2. That the expenditure of $210,517.98, or so much thereof as may be n...
Click here for full text