Explanation
BACKGROUND: This legislation amends the 2005 Capital Improvements Budget and authorizes the Finance and Management Director to enter into contracts for wire and cable needed for the Division of Electricity's Italian Village Substation Project and other critical work in progress.
The Purchasing Office opened Solicitation No. SA001671 to establish Universal Term Contracts to meet the Division of Electricity's need for wire and cable. All bids received were deemed non-responsive by the Purchasing Office and therefore, no award could be made at that time. The process of formally bidding and establishing a contract would delay delivery of wire and cable until July or August. This would cause construction delays, potentially increase costs, and jeopardize the Division's ability to maintain the integrity of the distribution system.
The Division of Electricity received the Mayor's permission, from a letter dated January 20, 2006, to immediately purchase wire and cable and to work with the Purchasing Office to ensure a competitive process, for this project.
The Purchasing Office informally advertised this bid against Solicitation No. SO021924 and six bids were received. The bids have been reviewed and awards are recommended to the following vendors based upon the lowest, responsive and responsible bids received:
Vendor Contract Compliance
American Wire Group 65-1129415
Consolidated Electrical Distributors 95-2563864
The Division will also be establishing funds to provide cable needed for the Transportation Division to relocate electric poles in their Morse Road Improvement project. Additionally, the Division of Sewerage and Drainage is also encumbering funds, on behalf of the Division of Electricity, to compensate for cable provided to them for their Rhodes Park Project.
It is requested that this Ordinance be handled in an emergency manner in order to allow for the payment of the materia...
Click here for full text