Explanation
Background: This ordinance authorizes the Director of the Recreation and Parks Department modify an existing contract with Setterlin Building Company to provide construction services associated with the Cultural Arts Center Renovations 2025 Project. The modification amount being authorized by this ordinance is $110,306.55.
During the construction of improvements at the Cultural Arts Center, it was discovered that additional services are needed to improve the emergency and life safety mechanisms at the facility. The additional work will specifically include an additional door operator, facility signage, and an upgraded fire alarm system
The original project completion date of the project was April 26, 2026. The modified project completion date, as a result of the proposed modification, will be December 31, 2026.
Amount of Additional Funds: $110,306.55
Why Additional Services Were Not Foreseen: The extent of repairs needed for the life safety systems was not known when the project began. These necessary systems improvements were determined during renovations.
Why It Is Not In The Best Interest For The City To Award Additional Services Through Another Procurement Process: Procurement of these services through another process would result in an increased cost to the City and delay these necessary life safety services for the community.
How The Price For The Additional Services Was Determined: The pricing was requested from the contractor and reviewed with the project manager, department stakeholders, and the architect of record.
Principal Parties:
Setterlin Building Company
560 Harmon Avenue
Columbus, Ohio 43223
Jordan Spano, (614) 614-459-7077
Contract Compliance Number: 004372
Contract Compliance Expiration Date: April 9, 2027
Emergency Justification: Emergency action is requested in order to complete the life safety improvements as quickly as possible for the immediate benefit of those who use this facility.
Benefits to the Public: This uniqu...