header-left
File #: 0867-2005    Version: 1
Type: Ordinance Status: Passed
File created: 5/4/2005 In control: Utilities Committee
On agenda: 6/27/2005 Final action: 6/30/2005
Title: To authorize the Director of Public Utilities to enter into a professional engineering services with Evans, Mechwart, Hambleton and Tilton, Inc., in connection with the Sewer System Capacity Model Project; to authorize the appropriation, transfer and expenditure of $1,641,255.25 from the Sewer System Reserve Fund to the Sanitary Sewer Bond Fund; to amend the 2004 Capital Improvements Budget, for the Division of Sewerage and Drainage. ($1,641,255.25)
Date Ver.Action ByActionResultAction DetailsMeeting Details
6/30/20051 CITY CLERK Attest  Action details Meeting details
6/29/20051 MAYOR Signed  Action details Meeting details
6/27/20051 Columbus City Council ApprovedPass Action details Meeting details
6/27/20051 COUNCIL PRESIDENT PRO-TEM Signed  Action details Meeting details
6/20/20051 Columbus City Council Read for the First Time  Action details Meeting details
6/6/20051 Utilities Drafter Sent for Approval  Action details Meeting details
6/6/20051 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
6/6/20051 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
6/2/20051 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
6/1/20051 Utilities Drafter Sent for Approval  Action details Meeting details
6/1/20051 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
5/31/20051 CITY AUDITOR Reviewed and Approved  Action details Meeting details
5/31/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/31/20051 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
5/27/20051 Auditor Reviewer Reviewed and Approved  Action details Meeting details
5/26/20051 Auditor Reviewer Reviewed and Disapproved  Action details Meeting details
5/26/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/25/20051 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
5/25/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/16/20051 Finance Reviewer Reviewed and Disapproved  Action details Meeting details
5/16/20051 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/12/20051 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
5/12/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/11/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/11/20051 Utilities Reviewer Sent for Approval  Action details Meeting details
Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to enter into a contract with Evans, Mechwart, Hambleton and Tilton, Inc., for purposes of providing professional engineering services for Sewer Infrastructure Attribute Database Enhancement associated with the Division of Sewerage and Drainage's Sewer System Capacity Model Project formerly known as the Franklin/OSIS/Interconnector Project. The Division utilizes this computerized hydraulic model for purposes of analyzing the impact future development has upon the system; and to identify effects of rehabilitation and augmentation to the existing infrastructure.

The purpose of this contract will be to complete the final incorporation of all remaining attributes of the sanitary and combined system that have not had the infrastructure information entered for sewers down to 8-inches in diameter. Many of the other areas have had this data inputted as a part of recently conducted inflow/infiltration projects or the Sewer Evaluation Capacity Assurance Plan (SECAP) that were performed under separate contracts. These attributes include: the depth of the invert; top of casting; type of pipe; date of installation; and other technical data. This information is vital to increasing the Division's ability to determine what changes are the most economically beneficial to improving the infrastructure's performance.

2. PROCUREMENT INFORMATION:
This procurement was conducted in accordance with the Request For Statement of Proposals (RFP) process set forth in Section 329.14, Columbus City Codes, 1959. The process was conducted as follows:
a. Written notice of need was made to City Council on October 31, 2004.
b. The RFP was published in the "City Bulletin" in consecutive weekly issues from November 20, 2004 through November 27, 2004.
c. Technical Proposals were received on December 3, 2004 from two firms, both active status firms.
d. Both firms submitting technical proposals ...

Click here for full text