Bids were received by the Recreation and Parks Department on October 30, 2003, for the North Bank Park - Issue B Project, as follows:
Status Amount
George J. Igel & Company Majority $2,111,315.00
Kokosing Construction Majority $2,132,000.00
Trucco Construction Majority $2,336,000.00
Complete General Majority $2,339,000.00
Project description includes general conditions, temporary facilities, site demo, mass earthwork, river muck removal, sheet piling, walers, deadmen, auger cast pilings, pile caps, storm sewer, concrete walls, painting, pre-cast concrete cap, balance of bid pack and allowance.
The Contract Compliance Number for George J. Igel is #31-4214570.
The approximate cost of Recreation and Parks staff time on this project is $5,000.00 (03-025).
A contingency amount of $150,000.00 is being included in this project.
Emergency action is necessary to keep project on schedule with existing and future construction projects in this riverfront area.
Fiscal Impact:
$1,261,320.00 is required and budgeted within the Recreation and Parks Grant Fund
$1,000,000.00 is required and budgeted in the Voted 1995 and 1999 Street and Highway Bond Fund.
Title
To authorize and direct the Director of Recreation and Parks to enter into contract with George J. Igel & Company for the North Bank Park - Issue B Project, to authorize the expenditure of $1,266,315.00 from the Recreation and Parks Grant Fund and $1,000,000.00 from the Voted 1995 and 1999 Street and Highway Bond Fund, and to declare an emergency. ($2,266,315.00)
Body
WHEREAS, bids were received by the Recreation and Parks Department on October 30, 2003, and the contract for the North Bank Park - Issue B Project will be awarded on the basis of the lowest and best responsive and responsible bidder; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessa...
Click here for full text