1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to execute a contract with United Survey, Inc., for the construction of the Torrence/Colerain Area Sanitary Improvements Project. This project will rehabilitate approximately 21,093 lineal feet of eight to 21-inch diameter sanitary sewer lines serving homes within the project area that is located in the Clintonville Community. This contract will utilize trenchless technology methods to minimize the disruption to residences in the project area and to avoid the costlier method of traditional open trench sewer removal and replacement.
The Director of Public Utilities publicly opened five competitive bid proposals on January 18, 2006. The cumulative results of these bids were: United Survey, Inc.submitted a bid of $1,274,980.80; and Reynolds, Inc., submitted a bid of $1,414,528.80; Insituform Technologies submitted a bid of $1,435,080.00; Kokosing Construction, Inc. submitted a bid of $1,471,308.30; and American Water Services Underground submitted a bid of $1,772,820.00. The Engineer's Estimate for this project was $1,879,138.20. In order to fund this contract, it was necessary to wait until an OWDA Loan could be requested, approved and executed by the Ohio Water Development Authority. The OWDA Board approved this loan on May 25, 2006.
2. FISCAL IMPACT:
This legislation appropriates a total of $1,274,980.80 from the OWDA Loan that will be utilized for the subject project. Companion expenditure legislation will appropriate an additional amount to cover the cost of construction administration and inspection services.
3. EMERGENCY DESIGNATION:
The Division of Sewerage and Drainage is requesting City Council to consider this legislation an emergency measure in order to allow for the immediate commencement of this contract work that is necessary to rehabilitate nearly 21,093 lineal feet of sanitary sewer serving a residential area in the Clintonville communit...
Click here for full text