Title: To authorize the Director of Public Utilities to enter into a contract with the Righter Company for the Dublin Road Water Plant Disinfection and Miscellaneous Improvements Temporary Scrubber, for the Division of Water, to authorize the expenditure of $322,350.00 from the Waterworks Enlargement Voted 1991 Bonds Fund, to amend the 2004 C.I.B., and to declare an emergency. ($322,350.00)
Attachments: 1. DRWP_VicMap.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
5/18/20051 CITY CLERK Attest  Action details Meeting details
5/17/20051 ACTING MAYOR Signed  Action details Meeting details
5/16/20051 Columbus City Council ApprovedPass Action details Meeting details
5/16/20051 COUNCIL PRESIDENT Signed  Action details Meeting details
5/6/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/6/20051 Auditor Reviewer Reviewed and Approved  Action details Meeting details
5/6/20051 CITY AUDITOR Reviewed and Approved  Action details Meeting details
5/6/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/6/20051 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
5/6/20051 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
5/5/20051 Utilities Drafter Sent for Approval  Action details Meeting details
5/5/20051 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/5/20051 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
5/2/20051 Finance Reviewer Reviewed and Disapproved  Action details Meeting details
4/28/20051 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
4/28/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/25/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/25/20051 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
4/21/20051 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
4/20/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/20/20051 Utilities Reviewer Reviewed and Approved  Action details Meeting details
4/20/20051 Utilities Drafter Sent for Approval  Action details Meeting details
4/20/20051 Utilities Reviewer Reviewed and Approved  Action details Meeting details
4/19/20051 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

BACKGROUND: Improvements to incorporate a chlorine gas scrubber system at the Dublin Road Water Plant will provide compliance with all applicable codes, as well as increase safety. The chlorine scrubber installation is a temporary measure as the Dublin Road Water Plant is currently being redesigned to utilize a different disinfection chemical in lieu of gaseous chlorine. It is anticipated that the new disinfection facility will be bid for construction in 2006, and on-line in 2007. This contract provides for the installation of the temporary scrubber and all associated miscellaneous electrical and mechanical modifications to complete the installation.

The procurement of this contract was conducted in accordance with Section 329.09.

Competitive bids were received and opened at the office of the Director of Public Utilities on March 23, 2005. Of the five (5) bids received, the lowest responsive and responsible and best bidder was the Righter Company, Inc. The bid of Downing Construction Company was non-responsive due to failure to complete the requirements of TIER I - MANDATORY FACTOR M-5 Construction Trades Licenses / Certificates Required. The bid of Ameritcon, Inc. was non-responsive due to failure to provide a proposal bond amount of not less than 10% of their bid in accordance with CMSC 102.08. Bidders that are determined non-responsive to these mandatory factors shall not be considered for further evaluation under Tier II - Creditable Factors.

BIDDER AMOUNT

Downing Construction Co. , Baltimore, Ohio $289,275.00
Ameritcon, Inc., Dayton, Ohio $319,999.05
The Righter Company, Columbus, Ohio $322,350.00
Reynolds, Inc., Orleans, Indiana $343,350.00
Kokosing Construction Co., Fredricktown, Ohio $350,385.00


EMERGENCY: Emergency legislation is being requested to install this temporary chlorine gas scrubber system as soon as possible for the increased safety of the plant.

FISCAL IMP...