Explanation
Background: This ordinance authorizes The Public Service Director to enter into an agreement with the Ohio Department of Transportation (ODOT) for the reconstruction of the curbs and sidewalks on Hudson Street over I-71, lying within the City of Columbus. Specifically the bridge deck and sidewalks will be patched with concrete, the existing asphalt patches on the sidewalks will be removed, and the entire area will be cleaned.
Emergency action is requested in order to meet ODOT's schedule and have this work completed this year. In order to do this, the agreement needs to be returned to ODOT at which time the construction will begin.
Fiscal Impact: The estimated cost of construction for this project is $30,000.00. The total share of the cost for the City is $15,000.00. Funds for the City's share of this project are available due to encumbrance cancellations for completed projects within the 1995, 1999, 2004 Voted Streets and Highways Fund.
Title
To amend the 2007 C.I.B.; to authorize the transfer of funds between projects within the Voted 1995, 1999, 2004 Streets and Highways Fund; to authorize the expenditure of $15,000.00 within the Voted 1995, 1999, 2004 Streets and Highways Fund; to authorize the Public Service Director to enter into agreement with the Director of the Ohio Department of Transportation for the Hudson Street over I-71 curb and sidewalk project for the Transportation Division; and to declare an emergency. ($15,000.00)
Body
The following ordinance enacted by the City of Columbus, Ohio, hereinafter referred to as the Legislative Authority or Local Public Agency or "LPA", in the matter of the stated described project.
WHEREAS, this project consists repairing the curbs and sidewalks on the Hudson Street Bridge over I-71 by ODOT crews; and
WHEREAS, the LPA shall cooperate with the Director of The Ohio Department of Transportation (ODOT) in the above described project as follows:
The City agrees...