Explanation
The Department of Public Utilities entered into a contract with GS&P/OH, Inc., an affiliate of Gresham, Smith and Partners, to provide guidance through an Environmental Management System (EMS) development and implementation process and provide environmental management system development and implementation assistance when requested by the Department. The EMS establishes a well-defined environmental program structure, through the identification of roles and responsibilities of DPU staff and the adoption of policies, training, and procedures, to achieve long-term environmental regulatory compliance and reduce the Department's overall environmental impact. This contract was the result of a Request for Proposal received on July 31, 2008. The original contract covers a three-year period with each phase subject to review and approval by the City Council, the Mayor, and the Auditor's certification of funds.
This is the third modification of the contract. This phase will cover the costs associated with facility emergency preparedness and Spill Prevention Control and Countermeasure ("SPCC") compliance, which was not planned in the original contract. All terms and conditions of the original agreement remain in full force and effect.
SUPPLIER: GS&P/OH, Inc 62-1736493, expires February 05, 2012
GS&P/OH, Inc. does not hold MBE/FBE status.
1. Amount of additional funds: The amount of additional funds needed for these additional services is $75,000. The original contract ("Phase 1") was established for $400,000.00. Modification #1 ("Phase 2") was in the amount of $300,000.00. Modification #2 ("Phase 3") was in the amount of $250,000.00. The total cost of the original contract, modifications #1 and #2 and this modification is $1,025,000.00. The modification of the maximum monetary obligation under this contract represents funding added during the contract period for costs related to additional compliance-related services. The need for increase...
Click here for full text