Explanation
1. BACKGROUND: This legislation allows the Department of Public Utilities to reimburse the Department of Public Service for design work performed on behalf of Public Utilities for the Glick Road Overlay Project.
This project provides for the repair and restoration of the bridge deck on Glick Road Bridge at O'Shaughnessy Dam. The current bridge was constructed in 1992 and the deck is showing signs of wear. There are potholes that require frequent patching and have exposed reinforcing steel which is beginning to show signs of deterioration. This is a heavily utilized roadway that is constructed on top of the O'Shaughnessy Dam which is an important component of the City of Columbus Water Supply.
The Department of Public Utilities agreed to reimburse the Department of Public Service once the work was completed and final costs were known.
2. FISCAL IMPACT: Funds for this reimbursement are included in the Water Works Enlargement Voted Bonds Fund. The Department of Public Service shall submit an internal bill to the Auditor’s Office upon passage by City Council.
Title
To authorize the Director of Public Utilities to reimburse the Department of Public Service for design work performed on behalf of Public Utilities for the Glick Road Overlay Project; and to authorize an expenditure up to $40,842.32 from the Water Works Enlargement Voted Bonds Fund. ($40,842.32)
Body
WHEREAS, the Department of Public Service performed design work on behalf of the Department of Public Utilities for the Glick Road Overlay Project; and
WHEREAS, the Department of Public Utilities agreed to reimburse Public Service for this work; and
WHEREAS, it is necessary for this Council to authorize an expenditure of funds from the Water Works Enlargement Voted Bonds Fund, for the Division of Water; and
WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Water, to reimburse the Department of Public Service for des...
Click here for full text