File #: 0527-2024    Version: 1
Type: Ordinance Status: Passed
File created: 2/12/2024 In control: Public Utilities & Sustainability Committee
On agenda: 3/25/2024 Final action: 3/27/2024
Title: To authorize the Director of Public Utilities to enter into a construction contract with Elite Excavating Company of Ohio, Inc., for the Elizabeth Avenue Area Water Line Improvements project; to amend the 2023 Capital Improvements Budget; to authorize the appropriation and transfer of funds from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund; to authorize the appropriation and expenditure of up to $4,327,985.75 from the Water Supply Revolving Loan Account Fund for the contract; and to authorize the expenditure of up to $2,000.00 from the Water Bond Fund to pay for construction administration and inspection expenses for the project. ($4,329,985.75)
Indexes: MBE Participation, WBE Participation
Attachments: 1. ORD 0527-2024 Vicinity Map (Elizabeth).pdf, 2. ORD 0527-2024 Utilization Reporting Form.pdf, 3. ORD 0527-2024 Accounting Template, 4. CAP Ohio Reg.PDF, 5. ORD 0527-2024 Stone Environmental.PDF, 6. ORD 0527-2024 CAP Ohio Reg.PDF
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Elite Excavating Company of Ohio, Inc., for the Elizabeth Avenue Area Water Line Improvements, CIP #690236-100132, in an amount up to $4,327,985.75, and to encumber funds with the Department of Public Service for construction administration and inspection services in an amount up to $2,000.00, for a total expenditure of $4,329,985.75.

The work consists of rehabilitating approximately 9,500 linear feet of 6-inch and 8-inch water mains, service transfer work and other such work as may be necessary to complete the contract, in accordance with the drawings, technical specifications, special provisions, and City of Columbus Construction and Material Specifications as set forth in the Invitation For Bid (IFB).

The Columbus Community is “57 - Mid-East Area” and includes the following streets: Elizabeth Ave, Brownlee Ave, Brookway Road, Aven Drive, Scottwood Road, Kirkwood Road, Talisman Court, and Burnaby Drive.

TIMELINE:
All work shall be complete within 365 calendar days from the Notice to Proceed. The City anticipates issuing a Notice to Proceed in April 2024.

ESTIMATED COST OF PROJECT:
The bid amount and proposed award amount is $4,327,985.75, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract if unforeseen difficulties are encountered.

Cost summary:

Original Contract $ 4,327,985.75
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $ 4,327,985.75
DPS Prevailing Wage Administration $ 2,000.00
$ 4,329,985.75

2. ECONOMIC IMPAC...