File #: 3369-2024    Version: 1
Type: Ordinance Status: Passed
File created: 11/25/2024 In control: Public Safety & Criminal Justice Committee
On agenda: 12/16/2024 Final action: 12/18/2024
Title: To amend the 2024 Capital Improvement Budget; to authorize the transfer of funds within the Safety G.O. Bonds Fund, Fund 7701; to authorize the Director of the Department of Public Safety to enter into an agreement with Tri County Tower, LLC for removal of an existing radio tower and design and construction of a new radio tower; to waive the competitive bidding provisions of the Columbus City Code; to authorize the expenditure of $373,224.30 from the Safety G.O. Bonds Fund; and to declare an emergency. ($373,224.30)
Attachments: 1. 3369-2024 Tri-County COC Water Tank Antenna Removal Only, 2. 3369-2024 Tri-County COC Budgetary Proposal- Updated, 3. 3369-2024 Bid Waiver, 4. 3369-2024 Financial Coding
Explanation

BACKGROUND: This ordinance authorizes the Director of the Department of Public Safety to enter into an agreement with Tri County Tower, LLC for removal, decommissioning, and disposal of an existing radio tower and design and construction of a new tower on property owned by the City of Columbus at 6502 E. Broad St.

The Department of Public Safety currently has a radio tower mounted on top of a water tank at 6502 E. Broad St. The Department of Public Utilities, Division of Water, plans to repaint the water tank in 2025. The Department of Public Safety will be required to remove their radio tower from atop the water tank as part of this planned project. When comparing costs of renting a temporary radio tower and eventually mounting the existing tower back on the water tank vs. constructing a new radio tower, the Department of Public Safety determined that it will be more cost effective in the long run to construct a new radio tower. This radio tower is part of the Division of Support Services' telecommunications network which provides critical 800 MHz communication services throughout the City of Columbus for public safety forces.

A committee comprised of employees from the Department of Public Safety's Director's Office and Division of Support Services solicited quotes from various qualified vendors for this project. Tri County Tower, LLC quoted a total cost of $373,224.30, which includes $90,000.00 in contingency funding, which may be needed depending upon the results of the core sampling and soil analysis. Hayden Tower Service quoted a total cost of $449,339.00. Motorola quoted a total cost of $793,568.00.

Bid Information - This purchase is recommended to be made with a waiver of formal bidding requirements, due to the deadline for project completion and the vast difference in pricing between the quotes received.

Emergency Designation: Emergency legislation is requested because of the need to get this agreement implemented as soon as pos...