Legislation Details

File #: 2913-2026    Version: 1
Type: Ordinance Status: First Reading
File created: 10/13/2026 In control: Public Utilities & Sustainability Committee
On agenda: 11/16/2026 Final action:
Title: To authorize the Director of Columbus Water and Power to enter into a construction contract with BLD Services, LLC, for the Later Lining - Blueprint Clintonville 3 Project 1; to appropriate funds within the Sanitary Revolving Loan Fund; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $10,407,206.90 from the Sanitary Revolving Loan Fund and the Sanitary Bond Fund to pay for the project. ($10,407,206.90)
Indexes: MBE Participation
Attachments: 1. ORD 2913-2026 SOS.pdf, 2. ORD 2913-2026 Utilization Reporting Form.pdf, 3. ORD 2913-2026 Accounting Template.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Columbus Water and Power to enter into a construction contract with BLD Services, LLC for Water Reclamation (Sanitary Sewers) for the Lateral Lining- Blueprint Clintonville 3 Project 1, CIP #650872-139001, in an amount up to $10,405,206.90; and to encumber funds with the Columbus Power & Water for construction administration and inspection (prevailing wage) services in an amount up to $2,000.00, for a total expenditure of $10,407,206.90.

This project will install and/or repair lateral liners and sanitary services in residential areas. The liners will reduce inflow from storm and groundwater into the sewer. This will help the City meet its Sanitary Sewer Overflow consent order.

The Community Area for this ordinance will be 10- Clintonville

TIMELINE: Contract work is required to be Substantially Complete in a manner acceptable to the City within 600 days from the date that a Notice To Proceed (NTP) is given by the City. Final Acceptance shall be achieved within 700 days of NTP.

ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $10,405,206.90, including a 20% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

Cost summary:

Original Contract $ 10,405,206.90
Future Anticipated Needs $ 0.00
Prevailing Wage Services $ 2,000.00
CONTRACT TOTAL $ 10,407,206.90

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
This project will provide lining ...