File #: 2053-2006    Version:
Type: Ordinance Status: Passed
File created: 11/8/2006 In control: Utilities Committee
On agenda: 12/11/2006 Final action: 12/13/2006
Title: To authorize the Director of Public Utilities to enter into a planned modification of the contract with CH2M Hill , for Professional Engineering Services for the Hap Cremean Water Plant Sludge Pump Station Renovations and Electrical Upgrades, for the Division of Power and Water , and to authorize the expenditure of $4,318,963.00 from Waterworks Enlargement Voted 1991 Bonds Fund and to declare an emergency. ($4,318,963.00)
Attachments: 1. HCWP_VicMap.pdf, 2. Modification 11 06.pdf, 3. Project Schedule 11 06.pdf, 4. RFSQ Summary HCWP Sludge Sta w addresses.pdf, 5. Information to be included in Contracting Legislation HCWP Sludge PS Eng Mod.pdf, 6. HCWPSLUDGESCOPE.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/13/20062 MAYOR Signed  Action details Meeting details
12/13/20062 CITY CLERK Attest  Action details Meeting details
12/11/20061 Columbus City Council Amended to EmergencyPass Action details Meeting details
12/11/20062 Columbus City Council Approved as AmendedPass Action details Meeting details
12/11/20062 COUNCIL PRESIDENT Signed  Action details Meeting details
12/4/20061 Columbus City Council Read for the First Time  Action details Meeting details
11/17/20061 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/17/20061 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/16/20061 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/16/20061 Utilities Drafter Sent for Approval  Action details Meeting details
11/16/20061 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/16/20061 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/16/20061 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/16/20061 Utilities Drafter Sent for Approval  Action details Meeting details
11/16/20061 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/16/20061 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/16/20061 Utilities Drafter Sent for Approval  Action details Meeting details
11/13/20061 Utilities Reviewer Sent for Approval  Action details Meeting details
11/13/20061 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/13/20061 Utilities Drafter Sent for Approval  Action details Meeting details
11/13/20061 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
11/10/20061 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/10/20061 Utilities Drafter Sent for Approval  Action details Meeting details
11/8/20061 Utilities Drafter Sent for Approval  Action details Meeting details
11/8/20061 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

BACKGROUND: The coagulation and lime softening treatment processes at the Hap Cremean Water Plant are the primary source of sludge solids. This project shall address the conveyance of these sludge solids from the treatment basin discharge to the Plant lagoons and the McKinley Avenue quarry. This project shall provide engineering services necessary for and incident to the provision of sludge conveyance and pumping upgrades and electrical upgrades at the Hap Cremean Water Plant and the existing 17-mile long sludge force main to the McKinley Avenue Quarry. The selected professional service firm will provide all office and field services necessary to prepare technical reports and design documents for construction bidding, and provide technical and administrative services and field project representation during construction. This contract modification will provide for engineering design for changes which were implemented after the Value Engineering process and after discussions with Water Treatment Plant staff; and to provide construction administration and construction inspection services.

CC 329.16 CONTRACT MODIFICATIONS:
1. Amount of additional funds to be expended under this modification: $4,318,963.00
2. The services identified to be included in this contract modification were identified in the original contract however costs for these services were not identified at that time. It was not possible to accurately estimate the costs to perform these tasks until the first phase of the work was completed. The original authorizing legislation (#0474-2005) indicated the expenditure for construction administration services would be authorized by a future modification when the scope of services could be better defined.
3. The work under this contract modification is a continuation of work previously performed by the Consultant; therefore, no other processes were used for procurement of these services.
4. The cost of this modificati...