Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Berglund Construction Company for the Jackson Pike Waste Water Treatment Plant (JPWWTP) Incinerator Building Rehabilitation project, CIP #650260-102016, in an amount up to $2,750,000.00, and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $2,752,000.00.
This project will replace the Incinerator Building roof, repair the building façade, repair any foundation cracking, and replace the fallen rubble stone and repair any other damages to the stone facade. Protective coatings on the building will be replaced and the HVAC equipment and electrical systems will be rehabilitated or replaced to bring the building up to current codes.
Planning Area - 59 - Southwest.
TIMELINE: Contract work is required to be completed in a manner acceptable to the City within 320 days from the date that a Notice to Proceed (NTP) is given by the City. NTP is anticipated on or about August 1, 2024.
ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $2,750,000.00, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.
Cost summary:
Original Contract $2,750,000.00
Future Anticipated Needs $ 0.00
CONTRACT TOTAL $2,750,000.00
Prevailing Wage Charge $ 2,000.00
$2,752,000.00