1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to execute a contract modification to the Sewer System Engineering Section's Construction Administration and Inspection Services Agreement with DLZ Ohio, Inc. This modification will increase the funding of the contract services by an additional $257,000.00 for construction administration services for sanitary sewer system projects. These projects typically involve the replacement and or rehabilitation of sanitary and combined sewer infrastructure under both emergency and expedited circumstances. This is one of two construction administration and inspection services contracts that the Sewer System Engineering Section utilizes. The other firm is R.D. Zande & Associates, Inc.
2. CONTRACT MODIFICATION INFORMATION:
This contract was originally procured to provide services for the fiscal years of 2002-2004. The Division anticipates undertaking a new procurement in early 2005 for the replacement of these contract services. The contract total including this modification is $777,000.00. The Division has determined that it is appropriate augment city personnel by utilizing these contracted services on a routine basis. The cost of these services is consistent with those provided for under the existing agreement.
3. FISCAL IMPACT:
This modification will be funded utilizing $207,000.00 of 1991 Voted Bond Funds for purposes of providing payment of work specific to capital improvements. An additional $50,000.00 will be funded from the Sewerage System Operating Fund for smaller scope projects. The project account funds transferred within this ordinance are residual funds from a project that is being funded through an OWDA loan.
4. EMERGENCY LEGISLATION:
The Division of Sewerage and Drainage is requesting Council to pass this ordinance as an emergency measure which is required to allow for the continuation of these services that are required to address emergency sanitary and combine...
Click here for full text