File #: 0761-2011    Version: 1
Type: Ordinance Status: Passed
File created: 5/9/2011 In control: Finance Committee
On agenda: 6/6/2011 Final action: 6/8/2011
Title: To amend the 2011 Capital Improvement Budget; to authorize the City Auditor to transfer $560,000.00 between projects within the Department of Public Utilities Sanitary B.A.B.'s (Build America Bonds) Fund; to authorize the Finance and Management Director to enter into a contract on behalf of the Office of Construction Management with Messer Construction Company for renovation for the Fairwood vehicle maintenance facility, 1250 Fairwood Avenue; to authorize the expenditure of $560,000.00 from the Department of Public Utilities Sanitary B.A.B.'s (Build America Bonds) Fund; and to declare an emergency. ($560,000.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
6/8/20111 CITY CLERK Attest  Action details Meeting details
6/7/20111 MAYOR Signed  Action details Meeting details
6/6/20111 Columbus City Council ApprovedPass Action details Meeting details
6/6/20111 COUNCIL PRESIDENT Signed  Action details Meeting details
5/19/20111 Auditor Reviewer Reviewed and Approved  Action details Meeting details
5/19/20111 CITY AUDITOR Reviewed and Approved  Action details Meeting details
5/19/20111 Finance Drafter Sent for Approval  Action details Meeting details
5/19/20111 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
5/19/20111 Finance Drafter Sent to Clerk's Office for Council  Action details Meeting details
5/18/20111 EBOCO Reviewer Sent for Approval  Action details Meeting details
5/18/20111 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
5/18/20111 Finance Drafter Sent for Approval  Action details Meeting details
5/17/20111 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
5/17/20111 Finance Drafter Sent for Approval  Action details Meeting details
5/16/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/13/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/12/20111 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
5/12/20111 Utilities Reviewer Sent for Approval  Action details Meeting details
5/12/20111 Finance Drafter Sent for Approval  Action details Meeting details
5/10/20111 Utilities Reviewer Sent for Approval  Action details Meeting details
5/9/20111 Finance Drafter Sent for Approval  Action details Meeting details
5/9/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/9/20111 Finance Drafter Sent for Approval  Action details Meeting details
5/9/20111 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

BACKGROUND: This legislation authorizes the Director of Finance and Management to enter into a contract on behalf of the Office of Construction Management with Messer Construction Company for renovation for the Fairwood vehicle maintenance facility, 1250 Fairwood Avenue.

The work shall include upgrades to the existing vehicle maintenance area, HVAC and electrical systems and upgrades to the indoor truck parking bay and existing vehicle storage area. The upgrades are necessary to meet code requirements and to allow for compressed natural gas vehicle maintenance within this facility. The scope of the project includes, but is not limited to, additional ventilation fans, methane sensor system, and control work.

Formal bids were solicited and two companies submitted bids on April 20, 2011 as follows (1 ^MBE, 0 FBE):

Messer Construction $560,000.00
^Williamson Builders $592,549.00

The Office of Construction Management recommends the bid award be made to the most responsive and responsible bidder, Messer Construction Company.

Emergency action is necessary so installation of the additional ventilation system can begin quickly, thereby, permitting currently owned compressed natural gas fueled City vehicles and those soon to be acquired, to be safely serviced and maintained appropriately within the vehicle maintenance facility.

Messer Construction Co. Contract Compliance No. 31-0740877; expiration date July 12, 2012.

This company is not debarred according to the Federal Excluded Parties Listing or prohibited from being awarded a contract according to the Auditor of State's Unresolved Finding for recovery search.

Fiscal Impact: The cost of this contract is $560,000.00. This ordinance authorizes the transfer of $560,000.00 between projects within the Department of Public Utilities Sanitary B.A.B.'s (Build America Bonds) Fund. This legislation amends the 2011 Capital Improvement Budget to establish sufficient ...