header-left
File #: 0156-2007    Version: 1
Type: Ordinance Status: Passed
File created: 1/24/2007 In control: Public Service & Transportation Committee
On agenda: 3/12/2007 Final action: 3/15/2007
Title: To authorize the Public Service Director to enter into a contract for the Transportation Division with Columbus Asphalt Paving, Inc. for construction of the Sawmill/Billingsley Road Intersection Improvement project; to authorize the expenditure of $356,009.10 from the Voted 1995, 1999, 2004 Voted Streets and Highways Fund for the Transportation Division; and to declare an emergency. ($356,009.10).
Date Ver.Action ByActionResultAction DetailsMeeting Details
3/15/20071 CITY CLERK Attest  Action details Meeting details
3/14/20071 MAYOR Signed  Action details Meeting details
3/12/20071 Columbus City Council ApprovedPass Action details Meeting details
3/12/20071 COUNCIL PRESIDENT Signed  Action details Meeting details
3/2/20071 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
3/2/20071 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
3/2/20071 Service Reviewer Sent for Approval  Action details Meeting details
3/2/20071 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
3/2/20071 Service Reviewer Sent to Clerk's Office for Council  Action details Meeting details
3/1/20071 Auditor Reviewer Reviewed and Approved  Action details Meeting details
3/1/20071 CITY AUDITOR Reviewed and Approved  Action details Meeting details
3/1/20071 Service Reviewer Sent for Approval  Action details Meeting details
2/28/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
2/28/20071 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
2/28/20071 Service Reviewer Sent for Approval  Action details Meeting details
2/26/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
2/23/20071 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
2/6/20071 Service Drafter Sent for Approval  Action details Meeting details
2/6/20071 Service Reviewer Reviewed and Approved  Action details Meeting details
Explanation

Background: This legislation authorizes the City to enter into a contract in an amount up to $315,052.30 for the Sawmill/Billingsley Road Intersection Improvement project and to pay construction inspection costs up to $40,956.80.

This project consists of adding a northbound right hand turn lane on Sawmill Road south of Billingsley Road. The turn lane extends past the shopping center access road. In addition, a six-foot wide concrete sidewalk and ADA compliant curb ramps will be provided.

Following the construction of the Sawmill Road and I-270 Single Point Urban Interchange (SPUI), the intersection of Sawmill Road and Billingsley Road became a choke point for motorists, which to date continues to interfere with the operations of the SPUI and westbound traffic on I-270 east of Sawmill Road. Lengthening the existing northbound right turn lane onto Billingsley Road will provide relief to some of the traffic congestion along Sawmill Road in this segment. Design was initiated by the City with Prime Engineering in 2004. The construction plans were approved in 2005. Right-of-Way was acquired in 2006.

The estimated Notice to Proceed date is April, 2007. The project's construction has been given 45 days to be completed. The project was let by the Transportation Division and was advertised in the City Bulletin, Dodge Reports, and by the Builders Exchange. Eighteen bidders/suppliers were solicited (Sixteen majority, two minority) and twelve bids were received (ten majority, two minority) and tabulated on January 18, 2007 as follows:

Columbus Asphalt Paving, Inc. (Majority) $315,052.30
Trucco Construction Company (Majority) $335,412.23
Gaddis and Sons (Minority) $392,245.25
Strawser (Majority) $355,076.30
Danbert (Majority) $432,766.83
Darby Creek (Majority) ...

Click here for full text