header-left
File #: 1825-2018    Version: 1
Type: Ordinance Status: Passed
File created: 6/21/2018 In control: Public Utilities Committee
On agenda: 7/23/2018 Final action: 7/25/2018
Title: To authorize the Director of Public Utilities to transfer within, encumber and expend $234,034.85 for the Construction Inspection and Administration Services associated with the Rathbone Avenue Stormwater System Improvements Project to the City’s Department of Public Service from the Storm Recovery Zone Super Build America Bond Fund; and to amend the 2018 Capital Improvement Budget. ($234,034.85)
Attachments: 1. Funding Template Revised MJC
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to fund the construction inspection costs payable the City of Columbus Department of Public Service for the Rathbone Avenue Stormwater System Improvements Project 610805-100000. Construction for project was authorized by Ordinance 1305-2018 with George J. Igel & Co., Inc. The project requires construction inspection and administrative services. The Department of Public Service has agreed to provide these services.
2. PROJECT TIMELINE: The contracted work is required to be completed in a manner acceptable to the City within 365 days from the date that a Notice To Proceed (NTP) is given by the City.

3. CONTRACT COMPLIANCE NO.: The City of Columbus Department of Public Service is a governmental agency and contract compliance is not applicable.

4. Emergency Designation: Emergency designation is NOT requested at this time.

5. FISCAL IMPACT: This ordinance authorizes the encumbrance and expenditure of $234,034.85 from the Storm Sewer Bond Fund 6204 to the Department of Public Service.

Title

To authorize the Director of Public Utilities to transfer within, encumber and expend $234,034.85 for the Construction Inspection and Administration Services associated with the Rathbone Avenue Stormwater System Improvements Project to the City’s Department of Public Service from the Storm Recovery Zone Super Build America Bond Fund; and to amend the 2018 Capital Improvement Budget. ($234,034.85)

Body

WHEREAS, the work for the Rathbone Avenue Stormwater System Improvements Project requires construction inspection and administrative services; and

WHEREAS, the Department of Public Services has agreed to conduct the construction inspection and administration services in order to verify contractor adherence to the requirements of the City of Columbus Construction and Materials Specifications; and

WHEREAS, the Department of Public Services will incur costs with the inspection and ...

Click here for full text