Explanation
Background: This legislation authorizes the Transportation Division to enter into a contract for $3,036,633.34 for the Resurfacing 2004 Project 4 (OPWC) project and to pay construction inspection costs up to $364,396.00. This improvement details the planing and resurfacing of various streets and the construction of Americans with Disabilities Act (ADA)-conforming wheelchair ramps. This project has been given 180 calendar days for completion. The project was advertised in the Columbus City Bulletin and Dodge Reports and by the Builders Exchange and was let by the Transportation Division. Seven bidders/suppliers were solicited (6 majority, 1 minority) and six bids were received (6 majority, 0 minority) and tabulated on November 4, 2004 as follows:
Contractor / Bid
Strawser Paving Company, Incorporated / $3,036,633.34
Columbus Asphalt Pavement Company / $3,123,750.10
Decker Construction Company / $3,138,820.94
Shelly and Sands, Incorporated / $3,162,788.42
The Shelly Company / $3,232,466.81
Miller Pavement Maintenance / $3,247,741.14
The Transportation Division recommends that the contract be awarded to Strawser Paving Company, Incorporated, contract compliance #31-4412354 (expiring July 15, 2005), for the lowest, best, most responsive and most responsible bid. The Notice to Proceed will be issued in March 2005.
Fiscal Impact: The Transportation Division budgeted $15.5 million in the 2004 Capital Budget for resurfacing. The total cost for this contract including construction inspection is $3,401,029.34. Ohio Public Works Commission funding is available in the amount of $120,107.63 for wheelchair ramp construction associated with this project. The City-funded portion of the total expense is $3,280,921.71 and is budgeted within 2004 Capital Improvements Budget in the Resurfacing project in the 1995, 1999 Voted Streets and Highways Fund. This ordinance transfers the City match money to the Local Transportation Improvement Progra...