File #: 0290-2004    Version: 1
Type: Ordinance Status: Passed
File created: 2/2/2004 In control: Utilities Committee
On agenda: 3/29/2004 Final action: 4/1/2004
Title: To authorize the Director of Public Utilities to modify the professional engineering services contract with Malcolm Pirnie, Inc. for the Southerly Wastewater Treatment Plant New Headworks Project; to authorize the appropriation, transfer and expenditure of $3,792,000.00 from the Sewer System Reserve Fund to the Ohio Water Pollution Control Loan Fund; and to declare an emergency. ($3,792,000.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
4/1/20041 CITY CLERK Attest  Action details Meeting details
3/31/20041 MAYOR Signed  Action details Meeting details
3/29/20041 Columbus City Council ApprovedPass Action details Meeting details
3/29/20041 COUNCIL PRESIDENT Signed  Action details Meeting details
3/3/20041 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
3/3/20041 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
3/2/20041 Auditor Reviewer Contingent Within  Action details Meeting details
3/2/20041 CITY AUDITOR Reviewed and Approved  Action details Meeting details
3/2/20041 Utilities Drafter Sent for Approval  Action details Meeting details
2/26/20041 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
2/26/20041 Utilities Drafter Sent for Approval  Action details Meeting details
2/25/20041 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
2/23/20041 Utilities Drafter Sent for Approval  Action details Meeting details
2/20/20041 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
2/19/20041 Finance Reviewer Reviewed and Approved  Action details Meeting details
2/12/20041 Utilities Drafter Sent for Approval  Action details Meeting details
2/11/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
2/9/20041 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
2/5/20041 Utilities Reviewer Reviewed and Approved  Action details Meeting details
2/3/20041 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to modify the professional engineering services contract with Malcolm Pirnie, Inc. for engineering services that are required for the successful completion of the Southerly Wastewater Treatment Plant New Headworks Project. This legislation further requests Council to authorize the appropriation, transfer and expenditure of funds from the Sewer System Reserve Fund to the Ohio Water Pollution Control Loan Fund.

The purpose of this project is to construct a new raw sewage pump building at the Southerly Wastewater Treatment Plant. The existing, original headworks facility would require extensive renovation work to maintain reliable service. It is less expensive and more expeditious to replace the facilities. The new facility will provide additional flow capacity and expandability to the wastewater treatment facility. The sequencing of this project requires coordination with the recently commenced Big Walnut Augmentation Rickenbacker Interceptor Sewer Project which will connect to this project that is located along the northeastern boundary of the Southerly Wastewater Treatment Plant.

2. PROFESSIONAL ENGINEERING SERVICES CONTRACT MODIFICATION:
The subject modification is needed to provide engineering services during construction that are currently estimated to cost $3,792,000.00. The Division of Sewerage and Drainage has determined that these services cannot be performed by city personnel at this time, and has planned for the procurement of these services on a routine basis. The potential need for the additional work was foreseen and so stated in the original contract's legislation explanation. This additional work is a direct, logical extension of the work included in the contract and is required immediately. It is not deemed either feasible or reasonable to suspend work with the entities currently under contract and undertake continuation of the work under a new pr...

Click here for full text