Title: To authorize an amendment to the 2022 Capital Improvement Budget; to authorize a transfer of cash and appropriation between projects within the Water Bond Fund; to authorize the Director of Public Utilities to enter into a construction contract with Clearcreek Coatings for the North District East Tank 2023 Painting Improvements project; and to authorize the expenditure of up to $2,169,900.15 from the Water Bond Fund for the project. ($2,169,900.15)
Attachments: 1. ORD 0639-2023 Accounting Template, 2. ORD 0639-2023 Utilization Plan
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Clearcreek Coatings for the North District East Tank 2023 Painting Improvements project, CIP #690477-100018, in an amount up to $2,167,900.15, and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $2,169,900.15.

The Division of Water is responsible for providing quality water for consumer use and adequate volume for fire protection. There are currently 38 water tanks in the distribution system and 26 of them are maintained by the City of Columbus, Division of Water. This project provides painting improvements for the maintenance of a steel elevated water storage tank. Regular maintenance inspections have determined that the North District East tank exterior needs to be blasted and recoated at this time. The interior wet and dry area coating systems also need to be blasted and recoated. The project will include various safety improvements such as fall protection tie-off lugs on the roof and a rooftop handrail opening safety gate. These improvements will keep this tank in optimal condition and prolong its service life.

In addition to the above work, milling and resurfacing of the Asphalt driveway/parking area for the North District tanks parcel is included as a part of this contract along with the task to overcoat the Smoky Row - East Tank exterior roof and the painting of the ladder platform of the Westgate - West Tank.
The Community Planning Areas are: 39 - Clintonville; 31 - Far Northwest; 53 - Greater Hilltop.

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
These improvements will keep this tank in optimal condition and prolong its service life. Special consideration towards environmentally friendly operations will be implemented, one of which is the recycling of t...