Explanation
1. BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a construction contract with Deer Creek Excavating, LLC, in the amount of $1,495,056.04; to encumber funds with the Transportation Division for inspection, testing, and prevailing wage coordination services in the amount of $181,500.96; all in connection with the Safford/Union Area Stormwater System and Water Line Improvements Projects.
This project includes $989,575.00 for Stormwater System Improvements as directed by the Project Engineer, which will be paid from the Storm Build America Bonds Fund and the Storm Sewer Bonds Fund; and $686,982.00 for Water Line Improvements as directed by the Project Engineer, which will be paid from the Water Build America Bonds Fund.
2. CONSTRUCTION CONTRACT AWARD: The Director of Public Utilities publicly opened twelve (12) bids on December 1, 2010. These bids were received from: Deer Creek-$1,495,056.04, Underground Utilities-$1,788,616.34, Eramo-$1,804,910.71, Connie-$1,849,157.08, Elite-$1,898,693.42, Double Z-$1,933,683.48, Seals-$1,991,830.04, Savko-$2,046,018.68, Columbus Asphalt-$2,235,078.90, Complete General-$2,311,165.80, Danbert-$2,355,757.46 and Trucco-$2,404,330.84.
The lowest and best bid was from Deer Creek Excavating, LLC, for $1,495,056.04. Additional information regarding each bidder, description of work, contract timeframe, detailed amounts and sub-contractors can be found on the attached Legislation Information Form.
Contract Compliance Information: 81-0651708, expires 11/02/11, Majority
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Deer Creek Excavating, LLC.
3. FISCAL IMPACT: There is sufficient cash and authority for the Stormwater portion of this project in both the Storm Build America Bonds Fund and the Storm Sewer Bonds Fund. A transfer of funds within the Water Build America Bonds Fund and an...