header-left
File #: 2331-2015    Version: 1
Type: Ordinance Status: Passed
File created: 9/14/2015 In control: Public Utilities Committee
On agenda: 10/26/2015 Final action: 10/29/2015
Title: To authorize the Director of Public Utilities to reimburse South-Western City Schools for the Holt Road 12” Water Line Project; for the Division of Water; to authorize an expenditure up to $21,740.21 from the Water Works Enlargement Voted Bonds Fund; and to authorize an amendment to the 2015 Capital Improvements Budget. ($21,740.21)
Attachments: 1. ORD 2331-2015 Information, 2. ORD 2331-2015 Costs, 3. ORD 2331-2015 map
Explanation

1. BACKGROUND: This legislation authorizes the Director of Public Utilities to reimburse South-Western City Schools (SWCS) for the Holt Road 12” Water Line Project, in an amount up to $21,740.21, (Division of Water Project Number 13-142).

SWCS’s developer requested to construct an 8-inch water main in Holt Road to serve a proposed school site. The City of Columbus, Division of Water required a 12-inch water main to be constructed in Holt Road for future extensions and development in the area. Therefore, per Columbus City Code Section 1105, the City will pay one hundred and ten (110) percent of the difference in the cost of the pipe, fittings and valves between the installation of an 8-inch water main and the 12-inch water main.

The Planning Area is “Westland” and includes the west side of Holt Road between Alkire Road and Big Run South Road.

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: The water line was constructed to serve a new South-Western City school.

3. BID INFORMATION: The South-Western City School District bid the project.

4. CONTRACT COMPLIANCE: 31-6402588 (local gov’t)

5. FISCAL IMPACT: There is sufficient funding within the Water Works Enlargement Voted Bonds Fund for this reimbursement, however, an amendment to the 2015 Capital Improvements Budget is necessary.


Title

To authorize the Director of Public Utilities to reimburse South-Western City Schools for the Holt Road 12” Water Line Project; for the Division of Water; to authorize an expenditure up to $21,740.21 from the Water Works Enlargement Voted Bonds Fund; and to authorize an amendment to the 2015 Capital Improvements Budget. ($21,740.21)

Body

WHEREAS, South-Western City School’s developer requested to construct an 8-inch water main in Holt Road to serve a proposed school site; and

WHEREAS, the Columbus Division of Water requires a 12-inch water main to be constructed for fu...

Click here for full text