Title: To authorize the City Auditor to make a change order, transfer and expenditure of $321,799.81 within the Sanitary Sewer Super Build America Bond Fund, Fund 669; to authorize the transfer within and the expenditure of $31,500.00 from the Sanitary Sewer General Obligation Bond Fund; to amend the 2012 Capital Improvement Budget; and to authorize the Director of Public Utilities to enter into contract with Prime Engineering Inc. and to declare an emergency. ($353,299.81)
Explanation

Background: This ordinance authorizes a change order of funds within the Sanitary Sewer Super Build America Bond Fund, Fund 669 and authorizes the Director of Public Utilities to enter into a contract with Prime Engineering Inc. to provide Construction Administration / Construction Inspection (CA/CI) services for the Scioto Main Trunk and West Relief Rehabilitation Project.
This change order authorizes that the total amount of cash as follows: $ $312,375.00 from CIP # 650715-100000 and $9,424.81 from 650100-100000. These amounts are being transferred to CIP # 650725-100001 for the Large Diameter Sewer Rehabilitation - Olentangy Main Trunk Sewer. This change order involves EL012629 for Construction Administration / Construction Inspection work authorized in Ordinance 0470-2011 for Prime Engineering Inc.
This legislation also authorizes the Director of Public Utilities to enter into a contract with Prime Engineering Inc. in the amount of $31,500.00 to provide Construction Administration / Construction Inspection (CA/CI) services for the Scioto Main Trunk and West Relief Rehabilitation Project, CIP 650696-100000.
Emergency Designation: The Department of Public Utilities is requesting an emergency designation at this time.

Contractor Compliance No.: Prime Engineering Inc. | 26-0546656 | 02/17/2014 | ASN

Fiscal Impact: This legislation authorizes the change order of $321,799.81 within the Sanitary Sewer Super Build America Fund, Fund 669 for EL012629; authorizes the transfer within and the expenditure of funds ($31,500.00) from the Sanitary Sewer General Obligation Bond Fund, Fund 664; and an amendment to the 2012 Capital Improvement Budget.