Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Service to enter into a contract for the construction of the Operation Safewalks - Joyce Avenue Phase 2 (OPWC CCY05). This is a joint project with the Department of Public Utilities, who will provide a portion of the funding for storm water improvements included in the project.
The work for this project consists of the reconstruction of a 0.53 mile portion of Joyce Avenue and the reconstruction of a 0.38 mile portion of 17th Avenue. This will consist of: pavement widening, water line installation, installation of street trees, drainage improvements, installation of pedestrian walks and a shared use path, replacement of existing traffic signals at Joyce Avenue/17th Avenue, the installation of a storm water system along 17th Avenue from Maloney Park to Brentnell Avenue, installation of detention
basins at Windsor Avenue/Joyce Avenue and on 17th Avenue.
The estimated Notice to Proceed date is April 2, 2014. The project was let by the Office of Support Services through Bid Express. Four bids (all majority) were received on February 11, 2014, and tabulated on February 12, 2014, as follows:
Company Name Bid Amt Majority/MBE/FBE
Shelly and Sands, Inc. $9,236,702.01 Majority
Complete General Construction Co. $9,442,697.97 Majority
Trucco Construction Co., Inc. $9,575,755.51 Majority
George J. Igel & Co., Inc. $10,147,526.59 Majority
Award is to be made to Shelly and Sands, Inc. for the amount of $9,236,702.01.
Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Shelly and Sands, Inc.
2. CONTRACT COMPLIANCE
The contract compliance number for Shelly and Sands, Inc. is 314351261 and expires 1/6/16.
3. FISCAL IMPACT
The City has been awarded a $2,500,000.00 grant b...