Title: To authorize the Director of Public Utilities to enter into a professional engineering agreement with American Structurepoint Inc. for the Alum Creek Trunk - South (Phase 2) Rehabilitation Project; to amend the 2020 CIB and to authorize an expenditure of up to $869,024.86 from the Sanitary General Obligation Bond Fund. ($869,024.86 )
Attachments: 1. ORD 1795-2021 Funding Template, 2. ORD 1795-2021 Utilization
Explanation

BACKGROUND: This project will provide for the rehabilitation of 8,918 lineal feet of 96” and 102” diameter reinforced concrete pipe and associated manholes via shotcrete rehabilitation methods. The sewer to be rehabilitated is located approximately along the alignment of Alum Creek between Watkins Road and I-70.

The Community Planning Area is 64- Far South

PROCUREMENT: The Department of Public Utilities advertised a Request for Proposals (RFP’s) for Alum Creek Trunk - South (Phase 2) Rehabilitation CIP #650725-100020 on the Vendor Services and Bonfire websites from April 26, 2021 to May 21, 2021. The city received three (3) responses from the following firms: American Structurepoint, DLZ, and Stantec. All proposals were evaluated in accordance with Columbus City Code Title 3, Chapter 329.28, and were scored according to competence to perform, past performance, and understanding of the project approach.

MULTI-YEAR CONTRACT: The Department anticipates requesting additional future renewals to this contract.

PROJECT TIMELINE: This contract is planned for renewals and will span multiple years, concluding in 2025.

Contract Compliance No.: 35-1127317 | MAJ | 7/16/2021| Vendor#: 007019

Emergency Designation: Emergency legislation is not requested at this time.

Economic Impact: This project will reduce the overall risk to the sanitary sewer collection system by rehabilitating one of the Division of Sewerage & Drainage’s most critical assets.

Fiscal Impact: This contract requires an expenditure of up to $869,024.86 from the Sanitary General Obligation Bond Fund 6109 and amends the 2020 Capital Improvement Budget.


Title

To authorize the Director of Public Utilities to enter into a professional engineering agreement with American Structurepoint Inc. for the Alum Creek Trunk - South (Phase 2) Rehabilitation Project; to amend the 2020 CIB and to authorize an expenditure of up to $869,024.86 from the Sanitary General Obl...