File #: 2030-2025    Version: 1
Type: Ordinance Status: Second Reading
File created: 7/10/2025 In control: Public Utilities & Sustainability Committee
On agenda: 9/29/2025 Final action:
Title: To authorize the Director of the Department of Public Utilities to enter into a professional engineering services contract with Jacobs Engineering Group Inc for the Southerly Water Reclamation Plant Switching Station Replacement project; to authorize the appropriation of funds within the Sanitary Revolving Loan Fund; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of $4,622,182.00 from the Sanitary Revolving Loan Fund for the contract. ($4,622,182.00)
Indexes: MBE Participation, WBE Participation
Attachments: 1. ORD 2030-2025 Accounting Template, 2. ORD 2030-2025 Utilization, 3. Business_Details (30)
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a contract through the City’s RFP process with Jacobs Engineering Group Inc for professional engineering services for the Southerly Water Reclamation Plant (SWRP) Switching Station Replacement project, CIP #650346-100004, in an amount up to $4,622,182.00.

This project is for Design Development services and will include a basis of design report, preliminary design report and 30% design drawings for the design and installation of a new Main Switching Station, Northeast Switching Station, Southeast Switching Station, and Raw Sewage Pump Switching Station. It will eventually also include relocation of the Division of Power (DOP) Substation, and radial distribution electrical system routing for the facility.

This project will be completed utilizing the Construction Manager at Risk (CMAR) delivery method.

Two future modifications will be requested. One modification will be requested at the completion of design development and a second will be requested for services during construction.

Community Planning Area: 64 - Far South
TIMELINE: The Design Development Services portion of the contract is anticipated to be completed within 12 months of issuing the notice to proceed. The notice to proceed is expected to be issued in October 2025 and the Design Development portion is scheduled to conclude in September of 2026. A future modification will be requested for the remainder of the design (Preconstruction Services). A second modification will be requested for Engineering Services during Construction. Currently, construction is anticipated to be for two years, concluding in September 2029. These are all estimated timelines. Work will continue on each phase until the work is completed and accepted by the City, even if this means work has to continue past an expected completion date.

ESTIMATED COST OF PROJECT: The proposed award amount is $4,622,182.00, inclu...