File #: 1722-2009    Version: 1
Type: Ordinance Status: Passed
File created: 12/15/2009 In control: Utilities Committee
On agenda: 1/11/2010 Final action: 1/14/2010
Title: To authorize the Director of Public Utilities to modify and increase the construction contract with George J. Igel & Co, Inc. in order to receive additional ARRA stimulus funding for the Reservoir Pollution Reduction Project; to authorize the appropriation and transfer of $85,339.66 from the Water System Reserve Fund to the Water Pollution Control Loan Fund (WPCLF); to authorize the expenditure of $85,339.66 from the Water Pollution Control Loan Fund (WPCLF); to authorize an amendment to the 2009 Capital Improvements Budget; and to declare an emergency. ($85,339.66)
Attachments: 1. ORD1722-2009 Legis. Info. Form.pdf, 2. ORD1722-2009 Adj. Qty's.xlsx
Date Ver.Action ByActionResultAction DetailsMeeting Details
1/14/20101 CITY CLERK Attest  Action details Meeting details
1/12/20101 MAYOR Signed  Action details Meeting details
1/11/20101 Columbus City Council ApprovedPass Action details Meeting details
1/11/20101 COUNCIL PRESIDENT Signed  Action details Meeting details
12/31/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/31/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
12/31/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
12/30/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
12/30/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
12/30/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/30/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
12/30/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
12/29/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/29/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
12/23/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
12/23/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
12/23/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/18/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
12/18/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/17/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/17/20091 Utilities Drafter Sent for Approval  Action details Meeting details
12/16/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
12/15/20091 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase the construction contract with George J. Igel & Co., Inc. for the Reservoir Pollution Reduction Project, for the Division of Power and Water. This project was funded from the American Recovery and Reinvestment Act of 2009 (ARRA), also known as the federal stimulus bill.

According to the Ohio EPA, this project was awarded additional ARRA stimulus funding. Since the Division of Power and Water was only going to receive $4,500,000.00 in ARRA stimulus funding, deductions were taken against the base bid amount in the original contract. Now that the Division is receiving additional funding, some of these deductions can be omitted and additional items can be performed.

The total amount of this modification is $85,339.66, a 1.84% increase to the original contract.

1. Amount of additional funds to be expended: $85,339.66
Original Contract Amount: $4,558,275.40
Amount of original contract and this modification: $4,643,615.06

2. Reasons additional goods/services could not be foreseen:
The Division was just notified by the Ohio EPA that this project was awarded additional ARRA stimulus funding.

3. Reason other procurement processes are not used:
The Division is receiving extra ARRA stimulus funding for this project. Since deductions had to be made against the base bid amount in the original contract, additional items are now able to be performed by the contractor, George J. Igel & Co., Inc. They were the best, lowest, most responsive responsible bidder.

4. How cost of modification was determined:
The Division is omitting various deduct options that were originally deducted from the original contract.

Contract Compliance Information: 31-4214570, expires 3/11/11, Majority

Emergency Designation: It is requested that this Ordinance be handled in an emergency manner as the Ohio EPA requires the contract to be in place before Feb...