Explanation
1. BACKGROUND
The Mid-Ohio Regional Planning Commission (MORPC) serves as staff to the District Three Public Works Integrating Committee. This committee provides input and makes recommendations to the Ohio Public Works Commission for fund distribution for the State Capital Improvement Program and the Local Transportation Improvement Program. MORPC's costs for Round 23 are prorated to local jurisdictions based on the total funds ultimately awarded to each jurisdiction. The Department Public Service, Division of Design and Construction, was awarded a total of $11,950,550.00 for the City Bridge Rehabilitation - Rich Street Bridge, Roadway Improvements - Riversouth Phase 2, and the Arterial Street Rehabilitation - Henderson Road projects. The Division's administrative cost as determined by MORPC is .19654% of this total, or $23,487.00 and is authorized by this legislation.
2. FISCAL IMPACT
Funding in the amount of $23,487.00 is available within the Street and Highway Improvement Fund for this cost.
3. EMERGENCY DESIGNATION
Emergency action is requested to authorize this expenditure as soon as possible in order to promote and be consistent with accurate accounting practices.
Title
To authorize the Director of Public Service to make payment to the Mid-Ohio Regional Planning Commission for staff support services rendered in connection with the State Capital Improvement Program and Local Transportation Improvement Program for the Division of Design and Construction; to appropriate funds within the Street and Highway Improvement Fund and transfer funds between the Street and Highway Improvement Fund to the State Issue II Street Project Fund and the Fed-State Highway Engineering Fund and to expend $23,487.00 from these funds for this purpose; and to declare an emergency. ($23,487.00)
Body
WHEREAS, the Mid-Ohio Regional Planning Commission (MORPC) renders staff support services to the District Three Public Works Integrating Commi...