Explanation
Background: The City of Columbus entered into a Design Agreement with Wagenbrenner Development, Inc. to design public right-of-way improvements in and around the former Columbus Coated Fabrics site. During the design phase it became apparent that a traffic study would be necessary to compare existing and projected conditions around the site in order to determine the need for traffic signals and additional traffic lanes. For this reason it is desirable to modify the existing design contract of $1,060,000 to include the completion of this study and to increase the dollar amount by $18,700 for a total contract amount of $1,078,700.
Fiscal Impact: $18,700 is available in capital Fund 742 Development G.O. Bonds.
Title
To authorize the Directors of Development and Public Service to amend the Design Agreement for the Columbus Coated Fabrics site with Wagenbrenner Development, Inc. by increasing the scope of work to include a traffic study of existing and projected conditions around the site and to increase the contract amount by $18,700; to amend the 2009 CIB; and to authorize the expenditure of $18,700.00 from the Development G.O. Bonds Fund. ($18,700)
Body
WHEREAS, Wagenbrenner Development, Inc. is under contract with the City as the developer of the Columbus Coated Fabrics site; and
WHEREAS, Ordinance 0043-2009 authorized the City to enter into a Design Agreement with the developer to design public right-of-way improvements in and around the site; and
WHEREAS, the design phase has identified potential traffic changes due to the redevelopment and the Department of Public Service has requested a traffic study be completed; and
WHEREAS, it is desirable by both the Wagenbrenner Development, Inc. and the City of Columbus to modify the existing contract in scope and dollars in order to complete the traffic study so traffic changes can be made while still in the design phase; and NOW, THEREFORE,
BE IT ORDAINED BY THE COUN...