Explanation
BACKGROUND: The Division of Power and Water, Department of Public Utilities entered into a contract with CH2M Hill for professional engineering services for the General Engineering Services - Supply Group, on December 27, 2006 under the authority of Ordinance No. 1845-2006 passed November 20, 2006. Provisions to extend this contract were included in the original contract. This modification provides for the second year of service.
CC 329.16 CONTRACT MODIFICATIONS:
1. Amount of additional funds to be expended under this modification: $300,000.00
2. Reasons additional goods/services could not be foreseen initially: Provisions for this contract extension (SECTION VI - AGREEMENT EXTENSION) were included in the contract between the Division of Power and Water and CH2M Hill
3. Reasons other procurement processes are not used: The City of Columbus reserved the right to extend work under the contract.
4. How cost of Modification was determined: The rates for services were specified in Schedule A of the contract.
FISCAL IMPACT: This project is included in the 2007 CIB and is being funded with current monies.
CONTRACT COMPLIANCE NUMBER: 59-0918189, effective through 6/24/08, Majority Firm.
Title
To authorize the Director of Public Utilities to enter into a planned contract modification with CH2M Hill for General Engineering Services - Water Supply Group, for the Division of Power and Water , to authorize the expenditure of $300,000.00 from the Waterworks Enlargement Voted 1991 Bonds Fund, to amend the 2007 C.I.B., and to authorize the City Auditor to transfer funds within the Waterworks Enlargement Voted 1991 Bonds Fund. ($300,000.00)
Body
WHEREAS, Contract No. EL-006697 was authorized by Ordinance No.1845-2006, passed November 20, 2006, was executed December 27, 2006 and approved by the City Attorney on January 2, 2007, and
WHEREAS, the original contract was for the General Engineering Services - Supply Group; ...
Click here for full text