Explanation
Background:
This ordinance will authorize the Director of Recreation and Parks to enter into a contract with Mid West Landscape for Maynard and Summit Park Improvements.
Five bids were received by the Recreation and Parks Department on August 21, 2007 for the Maynard and Summit Park Improvements as follows:
Status Amount Base Bid After Credits Base with Alternate #1
Mid West Landscape Majority $43,640.00 $41,490.00 $47,440.00
Republic Builders Majority $43,000.00 $43,000.00 $47,800.00
M&D Blacktop Majority $50,000.00 $48,280.00 $58,000.00
McDaniels Construction MBE $50,547.00 $48,397.00 $61,662.00
The Righer Co. Majority $66,400.00 $64,680.00 $69,370.00
Services will include demolition, asphalt overlay, concrete, site furnishings and landscaping.
A contingency amount of $2,560.00 is being included in this project
Contract Compliance Number for Mid West Landscape is 31-1690650.
Emergency action is necessary to allow project to commence prior to winter season.
Fiscal Impact:
$50,000.00 is budgeted in the Recreation and Parks Voted 1999/2004 Bond Fund to meet the financial obligation of this project.
Title
To authorize the Director of Recreation and Parks to enter into contract with Midwest Landscape for the Maynard and Summit Park Improvements project, to authorize the expenditure of $50,000.00 from the Recreation and Parks Voted bond fund, and to declare an emergency. ($50,000.00)
Body
WHEREAS, bids were received by the Recreation and Parks Department on August 21, 2007 and the contract for Maynard and Summit Park will be awarded on the basis of the lowest and best responsive and responsible bidder; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessary ...
Click here for full text