Explanation
BACKGROUND: This legislation authorizes the Finance and Management Director to modify a contract on behalf of the Facilities Management Division with Roto Rooter for plumbing repairs. The contract was formally bid in February 2010 (SA003498). Legislation was not necessary earlier because the total contracts in years one and two did not exceed $20,000.00. The contract term is April 1, 2011 through March 31, 2012. The contract encompasses all buildings under the purview of the Facilities Management Division. This contract modification will allow Finance and Management to replace an oil interceptor at the Division of Police at the Central Safety Building, 120 Marconi Boulevard.
The work is to include, but is not limited to, the replacement of the interceptor, removal and replacement of four traffic posts, re-piping, and re-concrete excavated area.
Emergency action is requested so that plumbing repairs can occur without interruption.
Roto Rooter Contract Compliance No. 42-0499300, expiration date March 3, 2012.
Fiscal Impact: This legislation authorizes an expenditure of $14,313.82 from the Safety Voted Bond Fund for the replacement of the oil interceptor and associated plumbing work for the Central Safety Building. There is no impact on the General Fund operating budget.
Title
To authorize the Finance and Management Director to modify a contract on behalf of the Facilities Management Division with Roto Rooter for plumbing repairs at the Central Safety Building; to authorize the expenditure of $14,313.82 from the Safety Voted Bond Fund; and to declare and emergency. ($14,313.82)
Body
WHEREAS, the Facilities Management Division formally bid a contract with Roto Rooter through SA003498; and
WHEREAS, it is necessary to modify said contract for the replacement of an oil interceptor at the Central Safety Building, 120 Marconi Boulevard; and
WHEREAS, an emergency exists in the usual daily operations of the Finance ...
Click here for full text