header-left
File #: 1331-2009    Version: 1
Type: Ordinance Status: Passed
File created: 10/6/2009 In control: Utilities Committee
On agenda: 10/19/2009 Final action: 10/20/2009
Title: To authorize the Director of Public Utilities to enter into contract with Complete General Construction Co. and to provide funding for the Department of Transportation for construction administration / inspection services and prevailing wages for the 2009 General Construction Contract Project; to authorize the appropriation and transfer of funds from the Sanitary Sewer Reserve Fund, to the Voted Sanitary Sewer Bond Fund, to authorize the expenditure of $1,854,156.00. from the Voted Sanitary Sewer Bond Fund, and to amend the 2009 Capital Improvement Budget; and to declare an emergency. ($1,854,156.00.)
Attachments: 1. 650745 Request for Legislation 100609.pdf, 2. 650745 Request for legislation_Director's form 100609.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
10/20/20091 MAYOR Signed  Action details Meeting details
10/20/20091 CITY CLERK Attest  Action details Meeting details
10/19/20091 Columbus City Council ApprovedPass Action details Meeting details
10/19/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
10/9/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
10/9/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
10/9/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/9/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
10/9/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
10/8/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/8/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
10/8/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
10/8/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/7/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
10/7/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
10/7/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/7/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/7/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/7/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
10/7/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/6/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/6/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/6/20091 Utilities Drafter Sent for Approval  Action details Meeting details
10/6/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation

1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to execute a construction contract with the Complete General Construction Co., in the amount of $1,611,440.00 for the construction of the 2009 General Construction Contract Project and for the Division of Sewerage and Drainage, provide funding for Department of Transportation for construction administration / inspection services and prevailing wages in the amount of $242,716.00; to authorize the appropriation and transfer of funds from the Sanitary Sewer Reserve Fund to the Voted Sanitary Sewer Bond Fund, to authorize the total expenditure of $1,854,156.00 from the Voted Sanitary Sewer Bond Fund, and to amend the 2009 Capital Improvement Budget.

The work to be completed by this contract consists of raising manhole frames or reconstructing manholes to grade, repair of State Route 315 storm inlets, and sewer point repairs and such other work as may be necessary to complete the contract in accordance with the plans and specifications. Work is to be completed within 365 calendar days after the effective date of the Notice to Proceed.

The Director of Public Utilities publicly opened five competitive bid proposals on September 2, 2009. Bids were submitted by Bale Contracting, Inc., Complete General Construction Co., Danbert Inc., George J. Igel & Co. Inc., and The Righter Co. Inc The bid order is listed as follows:

Complete General Construction. Co. | 31-4366382 | 01/30/2010 | $1,611,440.00
George J. Igel & Co., Inc. | 31-4214570 | 03/11/2011 | $1,695,575.00
Bale Contracting, Inc. | 31-0996994 | 05/23/2010 | $1,743,406.00
Danbert Inc. | 31-1029004 | 10/22/2010 | $1,746,055.54
The Righter Co., Inc. | 31-0889208 | 04/07/2011 | $2,358,900.00

2. FISCAL IMPACT:
This ordinance authorizes the transfer and appropriate funds from the Sanitary Sewer Reserve Fund to the Voted Sanitary Sewer Bond Fund; to authorize the expenditure of $1,854,156.00...