1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a planned contract modification for professional engineering services with Arcadis US, Inc., for the Parson Avenue Water Plant (PAWP) Wellfield Development project, CIP #690580-100000, in an amount up to $3,746,300.00.
The PAWP Wellfield Development (CIP 690580-100000) project will design and construct improvements to develop a new wellfield and associated raw waterline based on recommendations from the PAWP Concept Plan Update project. The plant currently has 6 active collector wells. The proposed well is to help offset the anticipated loss of wells and/or capacity reductions in the future. Proposed Collector Well 112 (CW112) is to be located south of PAWP on Parcel 34 (east of Parsons Avenue / north of London-Groveport Road / south of Big Walnut Creek). The raw waterline from CW112 will tie into the existing 42” raw waterline from CW106 along Parsons Avenue.
Preliminary and detailed engineering have been accomplished under this contract with Arcadis US, Inc. This modification is for Arcadis US, Inc., to provide Engineering Services During Construction.
The Parsons Avenue Water Plant services multiple Columbus Communities so this project is coded as “99-Citywide”.
TIMELINE:
Phase 1: (Preliminary Design) begin March 2022 and end September 2022.
Phase 2: (Detailed Design) to begin September 2022 and end December 2025
Phase 3: (Engineering Services During Construction) are scheduled to start 2nd quarter 2026 and be completed 2nd quarter 2028.
1.1. Amount of additional funds to be expended: $3,746,300.00
Cost summary:
Original Contract: $1,534,500.00 (ORD 0176-2022; PO316092)
Modification #1: $1,902,000.00 (ORD 2457-2023; PO416688)
Modification #2: $3,746,300.00 (Current)
CONTRACT TOTAL $7,182,800.00
1.2. Reason other procurement processes are not used:
This contract was bid through the City’s RFP process to provide professional services through th...